Monthly Local Let Maintenance Report For Houston District As Of Oct 16, 2017 Page 1 Of 11

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS IN BRAZORIA COUNTY
ToVARIOUS HWYS IN BRAZORIA COUNTY
CSJ6225-76-001
Proj IDRMC - 622576001
Work TypeCLEANING & SWEEPING HIGHWAYS
 
0.001236986.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days366
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ADENVIRON LLC
SUBCONTRACTOR(S) FOR CCSJ: 6225-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07111202
Totals236986.980.000.000.0

CountyHARRIS
HighwaySH0225
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EAST HARRIS COUNTY
CSJ6243-92-001
Proj IDRMC - 624392001
Work TypeCLEANING AND SEALING JOINTS AND CRACKS
 
0.001711300.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6243-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05131201
Totals711300.000.000.000.0

CountyWALLER
HighwayFM1488
FromVARIOUS ROADWAYS IN WALLER COUNTY
ToVARIOUS ROADWAYS IN WALLER COUNTY
CSJ6250-11-001
Proj IDRMC - 625011001
Work TypeDELINEATOR, OBJ MRKR & MAILBOXES
 
0.001201145.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
QUALLS SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6250-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01131204
Totals201145.000.000.000.0

CountyHARRIS
HighwayUS0059
FromVARIOUS HWYS IN NORTH HARRIS AREA
ToVARIOUS HWYS IN NORTH HARRIS AREA
CSJ6253-43-001
Proj IDRMC - 625343001
Work TypeROADSIDE MOWING
 
0.001126716.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days106
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PARRA INVESTMENTS
SUBCONTRACTOR(S) FOR CCSJ: 6253-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03131204
Totals126716.640.000.000.0

CountyHARRIS
HighwaySH0225
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EAST HARRIS COUNTY
CSJ6253-77-001
Proj IDRMC - 625377001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001270857.08312568.11100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-28-14
Work Began04-01-14
Work Completed09-30-16
Time Computed04-01-14
Contract Working Days158
Addl Days Granted0
Working Days Charged105
Percent Time Used66
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05131203
Totals270857.080.00312568.11100.0

CountyHARRIS
HighwayIH0010
From7600 WASHINGTON AVE
To6810 OLD KATY ROAD
CSJ6257-02-001
Proj IDSUP - 625702001
Work TypeBLDG & GROUNDS MAINT, OPERATION & REPAIR
 
0.0101554621.602913532.6699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-13
Work Began06-01-13
Work Completed
Time Computed06-01-13
Contract Working Days730
Addl Days Granted1,461
Working Days Charged1,463
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
ON OUR OWN SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05131233
Totals1554621.600.002913532.6699.9

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6261-50-001
Proj IDRMC - 626150001
Work TypeGUARDRAIL REPAIR
 
0.001250955.00178615.82100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-06-13
Work Began12-09-13
Work Completed12-09-14
Time Computed12-09-13
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6261-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10131201
Totals250955.000.00178615.82100.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6265-19-001
Proj IDRMC - 626519001
Work TypeCLEAN AND RESHAPE DITCHES
 
0.001126000.00151200.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-16-14
Work Began06-23-14
Work Completed06-26-15
Time Computed06-23-14
Contract Working Days365
Addl Days Granted0
Working Days Charged336
Percent Time Used92
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05141201
Totals126000.000.00151200.00100.0

CountyWALLER
HighwayFM1488
FromWALLER COUNTY MAINTENANCE OFFICE
ToWALLER COUNTY MAINTENANCE OFFICE
CSJ6267-22-001
Proj IDSUP - 626722001
Work TypeJANITORIAL MAINTENANCE
 
0.00130954.5628352.56100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-01-14
Work Completed12-31-15
Time Computed01-01-14
Contract Working Days730
Addl Days Granted0
Working Days Charged722
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6267-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12131232
Totals30954.560.0028352.56100.0

CountyHARRIS
HighwayUS0290
FromVARIOUS HIGHWAYS IN WEST HARRIS CO.
To.
CSJ6267-31-001
Proj IDRMC - 626731001
Work TypeMOWING
 
0.001258063.47276951.24100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-01-14
Work Began05-01-14
Work Completed06-25-16
Time Computed05-01-14
Contract Working Days150
Addl Days Granted27
Working Days Charged84
Percent Time Used47
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03141205
Totals258063.470.00276951.24100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6267-81-001
Proj IDRMC - 626781001
Work TypeREFL PAV MRK (GRAPHICS)
 
0.001220899.35222377.27100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-04-14
Work Began06-08-14
Work Completed06-08-15
Time Computed06-08-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03141206
Totals220899.350.00222377.27100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS HWYS WITHIN BRAZORIA COUNTY
ToVARIOUS HWYS WITHIN BRAZORIA COUNTY
CSJ6269-31-001
Proj IDRMC - 626931001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001224920.00246505.38100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-23-14
Work Began06-01-14
Work Completed06-01-15
Time Computed06-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-31-001
HOLES INCORPORATED (10.98)
Contract #04141206
Totals224920.000.00246505.38100.0

CountyGALVESTON
HighwaySH0146
FromVARIOUS HWYS IN GALVESTON COUNTY
ToVARIOUS HWYS IN GALVESTON COUNTY
CSJ6270-12-001
Proj IDRMC - 627012001
Work TypeASPHALT PAVEMENT REPAIR
 
0.001279475.00450909.85100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-14
Work Began10-29-14
Work Completed12-26-16
Time Computed10-27-14
Contract Working Days365
Addl Days Granted0
Working Days Charged309
Percent Time Used84
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-12-001
REPUBLIC TRAFFIC SAFETY, INC. (1.08)
Contract #08141201
Totals279475.000.00450909.85100.0

CountyBRAZORIA
HighwaySH0288
FromVARIOUS ROADWAYS IN BRAZORIA COUNTY
ToVARIOUS ROADWAYS IN BRAZORIA COUNTY
CSJ6271-61-001
Proj IDRMC - 627161001
Work TypeSIGN REPLACEMENT
 
0.001195739.86172542.73100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-02-14
Work Completed03-03-15
Time Computed10-02-14
Contract Working Days44
Addl Days Granted0
Working Days Charged56
Percent Time Used127
Contractor(s)
LONESTAR TRAFFIC SAFETY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07141202
Totals195739.860.00172542.73100.0

CountyHARRIS
HighwaySL0008
FromVARIOUS HWYS IN SOUTH HARRIS COUNTY
ToVARIOUS HWYS IN SOUTH HARRIS COUNTY
CSJ6274-00-001
Proj IDRMC - 627400001
Work TypeROADSIDE MOWING
 
0.001227772.73226518.18100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-07-15
Work Began06-01-15
Work Completed07-01-17
Time Computed06-01-15
Contract Working Days102
Addl Days Granted22
Working Days Charged124
Percent Time Used100
Contractor(s)
RELIANT SAND AND CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03151202
Totals227772.730.00226518.18100.0

CountyWALLER
HighwayFM1488
FromWALLER MAINTENANCE OFFICE
ToWALLER MAINTENANCE OFFICE
CSJ6274-73-001
Proj IDSUP - 627473001
Work TypeLANDSCAPE MAINTENANCE
 
0.00137840.1037386.0598.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-14
Work Completed
Time Computed07-01-14
Contract Working Days730
Addl Days Granted0
Working Days Charged725
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
DAVID & IVORY MINISTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6274-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141231
Totals37840.100.0037386.0598.8

CountyHARRIS
HighwayIH0010
FromVARIOUS HIGHWAYS IN WEST HARRIS CO.
To.
CSJ6274-89-001
Proj IDRMC - 627489001
Work TypeBRIDGE DECK REPAIR
 
0.001143500.00205108.16100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-01-15
Work Completed08-01-17
Time Computed08-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged724
Percent Time Used99
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01151201
Totals143500.000.00205108.16100.0

CountyHARRIS
HighwayIH0010
FromVARIOUS HWYS IN EAST HARRIS COUNTY
ToVARIOUS HWYS IN EAST HARRIS COUNTY
CSJ6275-12-001
Proj IDRMC - 627512001
Work TypeREFLECTIVE PAVEMENT MARKINGS (GRAPHICS)
 
0.001236547.20253994.03100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-20-15
Work Completed01-20-17
Time Computed01-20-15
Contract Working Days731
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12141201
Totals236547.200.00253994.03100.0

CountyHARRIS
HighwayUS0059
FromSAN JACINTO RIVER AT US 59
ToSAN JACINTO RIVER_AT US 59
CSJ6276-17-001
Proj IDRMC - 627617001
Work TypeREML & DISPL DRIFTWOOD & DEBRIS
 
0.001142500.00821075.04100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-11-15
Work Began06-18-15
Work Completed05-08-17
Time Computed05-18-15
Contract Working Days731
Addl Days Granted0
Working Days Charged704
Percent Time Used96
Contractor(s)
AFTERMATH DISASTER RECOVERY INC
SUBCONTRACTOR(S) FOR CCSJ: 6276-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02151201
Totals142500.000.00821075.04100.0

CountyHARRIS
HighwayIH0610
FromIH 610 SOUTH LOOP
ToAT SH 288
CSJ6277-72-001
Proj IDBPM - 627772001
Work TypeBRIDGE MAINTENANCE REPAIRS
 
0.001196035.25202464.94100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-12-16
Work Completed12-16-16
Time Computed08-12-16
Contract Working Days45
Addl Days Granted0
Working Days Charged31
Percent Time Used68
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161201
Totals196035.250.00202464.94100.0