Monthly State Let Construction Report For Houston District As Of Feb 09, 2018 Page 2 Of 10

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayUS 290 ETC
FromWEST OF FM 529
ToE OF W LITTLE YORK (SEGMENT 6)
CSJ0050-09-071
Proj IDNH 2013(082)
Work TypeGR, STRS, BASE AND PAVE
 
6.056110414015.10111772360.4397.5
Work Order02-13-13
Work Began02-27-13
Work Completed
Time Computed02-01-13
Contract Working Days1,170
Addl Days Granted0
Working Days Charged1,175
Percent Time Used100
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-09-071
ARANDA BROTHERS CONSTRUCTION, INC. (0.68)
BATTERSON,LLP (0.75)
ENVIRONMENTAL ALLIES, L.P. (0.10)
BORCO OF TEXAS, INC. (1.07)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (3.23)
CURB PLANET INC. (0.03)
D G MEDINA CONSTRUCTION, LLC (0.22)
FARR FOUNDATION, INC. (0.20)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.13)
HOUSTON SAWING & DRILLING (0.03)
INDUS CONSTRUCTION, L.P. (0.90)
J.H. PAINTING COMPANY (0.27)
KELLYSTONE, INC (0.03)
KOSSMAN CONTRACTING CO., INC. (0.08)
RDI FOUNDATION DRILLING (2.38)
R K STEPHENS CONSTRUCTION, LLC (1.04)
SPEEDY PAVING (0.25)
T & C CONSTRUCTION, INC. (3.02)
WILLOW CITY SIGN & RAIL, INC. (0.47)
LAZER CONSTRUCTION COMPANY, INC. (0.82)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.07)
STEEL EFFECTS (0.13)
NORTHWEST MATERIALS (0.08)
SPRINT SAND AND CLAY, LLC (1.47)
SOUTHERN CRUSHED CONCRETE LLC (1.42)
MAGNOLIA SERVICES INCORPORATED (0.17)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (5.96)
MEDCALF FABRICATION, INC. (0.09)
C & B REBAR CONSTRUCTION, INC. (0.01)
(OLD PRIME)BORING & TUNNELING COMPANY OF AMERICA, INC. (0.13)
PFEIFFER & SON LTD. (0.58)
BRUNDAGE-BONE (0.07)
VALLEY PLACERS, LLC (0.10)
BATTEN DRILLING, INC. (0.21)
WEBBER BARRIER SERVICES, LLC. (1.29)
S & S MASONRY,INC. (0.02)
AAR INCORPORATED (0.01)
CPAVE, INC. (0.02)
H & S COMPANY (0.01)
MBN ENTERPRISES LLC (1.11)
AGGREGATE TECHNOLOGIES, INC. (0.01)
NATIONAL FENCE CO. (0.00)
D.H. GRIFFIN OF TEXAS, INC. (0.08)
INTERSTATE IMPROVEMENT, INC. (0.90)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.31)
CHANCE CONTRACTING (0.00)
Contract #09123202
Totals110414015.10858928.22111772360.4397.5

CountyHARRIS
HighwaySH 3
FromAT FM 2351 AND AT SOUTH SHAVER ROAD
To.
CSJ0051-02-079
Proj IDNH 2013(541)
Work TypeADD RT LN, RR WORK, W/SIGNALS
 
0.5481755643.651579124.0889.9
Work Order10-30-14
Work Began08-06-15
Work Completed
Time Computed04-28-15
Contract Working Days132
Addl Days Granted0
Working Days Charged108
Percent Time Used81
Contractor(s)
TRIPLE B SERVICES LLP
SUBCONTRACTOR(S) FOR CCSJ: 0051-02-079
ROADSAFE TRAFFIC SYSTEMS, INC. (3.39)
CHAMPIONS HYDRO LAWN, INC. (0.22)
CENTRAL CONSTRUCTION SERVICES, INC. (0.05)
DUSTROL, INC. (3.66)
AGGREGATE TECHNOLOGIES, INC. (0.63)
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (11.12)
SILT SOLUTIONS, INC. (0.31)
BADGER DAYLIGHTING CORP. (0.37)
CANALES TRUCKING INC. (0.85)
WILLOW CITY SIGN & RAIL, INC. (2.07)
SCMU (2.99)
GMJ PAVING CO. (25.75)
CURB PLANET INC. (2.52)
Contract #08133232
Totals1755643.650.001579124.0889.9

CountyHARRIS
HighwaySH 3
FromAT FM 1959, AND
ToAT EL DORADO BLVD INTERSECTIONS(SB)
CSJ0051-02-100
Proj IDNH 1702(627)
Work TypeADD RIGHT TURN LANES
 
3.551345345.91119075.5634.4
Work Order09-21-17
Work Began01-02-18
Work Completed
Time Computed10-21-17
Contract Working Days60
Addl Days Granted0
Working Days Charged17
Percent Time Used28
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0051-02-100
LONESTAR TRAFFIC SAFETY, LLC (1.12)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (4.38)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (19.26)
BATTERSON,LLP (7.01)
Contract #08173222
Totals345345.91119075.56119075.5634.4

CountyGALVESTON
HighwaySH 3
FromAT SH 96
To.
CSJ0051-03-106
Proj IDSTP 1502(247)HES
Work TypeTS IMPRVMTS
 
0.750609218.50564783.8192.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-15
Work Began12-07-15
Work Completed
Time Computed11-14-15
Contract Working Days103
Addl Days Granted0
Working Days Charged102
Percent Time Used99
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0051-03-106
BAY CITY TRAFFIC (4.85)
Contract #06153226
Totals609218.500.00564783.8192.7

CountyFORT BEND
HighwayUS 59
FromWEST OF HAMLINK ROAD
ToWEST OF SPUR 10
CSJ0089-09-058
Proj IDC 89-9-58
Work TypeGR, STRS, BS & SURF
 
8.004100144090.3257571826.2857.4
Work Order01-06-16
Work Began01-18-16
Work Completed
Time Computed01-18-16
Contract Working Days919
Addl Days Granted0
Working Days Charged590
Percent Time Used64
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-09-058
BASE CONSTRUCTION (9.99)
CPAVE, INC. (0.24)
CREACOM, INC. (3.26)
ESSARY, HART & MACWILIAM,INC. (6.93)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.01)
INTERSTATE BARRICADES & MARKINGS, INC. (0.96)
QUALITY TURF FARMS, LC (2.08)
SCOTT DERR PAINTING CO, LLC (0.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.13)
BORTUNCO (0.23)
WASTE PARTNERS OF TEXAS, INC (0.07)
ANTIGO CONSTRUCTION, INC. (0.03)
Contract #12153001
Totals100144090.32846760.3057571826.2857.4

CountyFORT BEND
HighwayUS 59
FromWHARTON COUNTY LINE
ToW OF DARST RD
CSJ0089-09-067
Proj IDC 89-9-67
Work TypeGR, STRS, BS & SURF
 
2.77137743798.5513649846.8836.1
Work Order08-12-16
Work Began08-29-16
Work Completed
Time Computed08-29-16
Contract Working Days1,208
Addl Days Granted0
Working Days Charged400
Percent Time Used33
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-09-067
ALLSTATE SIGNAL & CONSTRUCTION, LLC (2.94)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.69)
WILLOW CITY SIGN & RAIL, INC. (2.12)
SCOTT DERR PAINTING CO (0.02)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.24)
EROSION PREVENTION PRODUCTS (0.50)
QUALITY TURF FARMS, LC (0.88)
DORAN STEEL, INC. (7.47)
WASTE PARTNERS OF TEXAS, INC (0.32)
Contract #07163001
Totals37743798.55125717.4813649846.8836.1

CountyMONTGOMERY
HighwaySH 75
FromGLADSTELL STREET
ToIH 45 UNDERPASS
CSJ0110-04-129
Proj IDSTP 1702(807)MM
Work TypeGR, BS, REMOVE STRM SWR & PAV
 
0.7201126255.63198853.7217.6
Work Order10-09-17
Work Began00-00-00
Work Completed
Time Computed01-07-18
Contract Working Days53
Addl Days Granted0
Working Days Charged9
Percent Time Used16
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0110-04-129
CEN TEX HYDROSEED, INC. (4.29)
J & M CONTRACTING COMPANY (18.69)
STRIPE LINES, INC. (2.02)
TEXOP CONSTRUCTION (1.43)
WATERS CONSTRUCTION CO., INC. (3.41)
WILLOW CITY SIGN & RAIL, INC. (3.15)
AREA WIDE PROTECTIVE, INC. (0.43)
Contract #08173211
Totals1126255.63198853.72198853.7217.6

CountyMONTGOMERY ETC
HighwayIH 45
FromMONTGOMERY COUNTY LINE
ToLOOP 336 SOUTH
CSJ0110-04-195
Proj IDNH 1502(618)
Work TypeLANDSCAPE DEVELOPMENT
 
47.4543256878.262590590.1279.5
Work Order12-04-15
Work Began03-29-16
Work Completed
Time Computed01-04-16
Contract Working Days120
Addl Days Granted6
Working Days Charged127
Percent Time Used100
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0110-04-195
G & A BORING (0.15)
Contract #08153238
Totals3256878.2633641.592590590.1279.5

CountyHARRIS
HighwayFM 521
FromIH 610
ToSOUTH OF BROADHURST
CSJ0111-01-092
Proj IDNH 1702(512)
Work TypeMILL, SC, TOM & PAV MARKS
 
5.6693070707.871228872.8640.0
Work Order10-26-17
Work Began11-06-17
Work Completed
Time Computed11-25-17
Contract Working Days143
Addl Days Granted0
Working Days Charged25
Percent Time Used17
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0111-01-092
PROFESSIONAL TRAFFIC CONTROL, LLC (4.09)
Contract #07173041
Totals3070707.872650.001228872.8640.0

CountyFORT BEND
HighwayFM 521
FromHARRIS COUNTY LINE
ToSOUTH OF FM 2234
CSJ0111-03-031
Proj IDNH 1702(416)
Work TypeGR, STRS, BS & SURF
 
1.53434567384.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days529
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PULICE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0111-03-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173221
Totals34567384.220.000.000.0

CountyBRAZORIA
HighwayBS 288B
FromCEMETERY ROAD
ToBASTROP BAYOU
CSJ0111-07-048
Proj IDSTP 2017(633)
Work TypePV REP & ACP O/L
 
10.1515258450.725360132.7399.9
Work Order03-08-17
Work Began04-17-17
Work Completed
Time Computed04-07-17
Contract Working Days151
Addl Days Granted0
Working Days Charged150
Percent Time Used99
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0111-07-048
THIRD COAST SERVICES LLC (7.52)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (3.30)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.62)
BATTERSON,LLP (4.06)
MAIN LANE INDUSTRIES LTD. (2.24)
HOLES INCORPORATED (0.19)
Contract #02173211
Totals5258450.720.005360132.7399.9

CountyHARRIS
HighwayUS 290
FromFM 2920
ToBADTKE ROAD (SEGMENT 12)
CSJ0114-12-007
Proj IDNH 2013(733)
Work TypeGR, STRS, BASE AND PAVE
 
6.52660092663.9656971618.1894.8
Work Order07-22-15
Work Began07-27-15
Work Completed
Time Computed10-21-15
Contract Working Days536
Addl Days Granted168
Working Days Charged638
Percent Time Used90
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-12-007
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.87)
MESA ROD BUSTERS, INC. (6.67)
PROFESSIONAL TRAFFIC CONTROL, LLC (1.43)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.00)
BASE CONSTRUCTION (3.36)
QUALITY TURF FARMS, LC (2.53)
BAY CITY TRAFFIC (0.35)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.34)
SCOTT DERR PAINTING CO (0.01)
CEN-TEX IRRIGATION SYSTEMS, INC. (0.14)
ADCOCK 4 INVESTMENTS, LLC, DBA BRADCO (0.20)
ROADWAY CONSTRUCTION, LLC (1.04)
FINE CURBS (0.03)
Contract #06153201
Totals60092663.961289984.7056971618.1894.8

CountyMONTGOMERY
HighwayIH 69
FromN. OF FM 2090
ToS. OF EAST RIVER
CSJ0177-05-093
Proj IDC 177-5-93
Work TypeGR, BASE AND PVT
 
1.4577416768.137864884.6999.9
Work Order12-01-15
Work Began01-18-16
Work Completed
Time Computed01-18-16
Contract Working Days248
Addl Days Granted0
Working Days Charged238
Percent Time Used95
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0177-05-093
CPAVE, INC. (0.58)
GMJ PAVING CO. (4.27)
MESA ROD BUSTERS, INC. (1.14)
SOUTHERN CRUSHED CONCRETE LLC (1.02)
STRIPE-A-LINE, INC. (0.59)
TEX OP CONSTRUCTION, LP (0.42)
THIRD COAST SERVICES LLC (2.74)
WILLOW CITY SIGN & RAIL, INC. (0.60)
A-1 EROSION CONTROL, LLC (0.09)
SILT SOLUTIONS, INC. (3.11)
LONESTAR TRAFFIC SAFETY, LLC (0.17)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.14)
SCOTT DERR PAINTING CO, LLC (0.02)
Contract #05153038
Totals7416768.1311899.907864884.6999.9

CountyMONTGOMERY
HighwayIH 69
FromHARRIS COUNTY
ToLIBERTY COUNTY LINE
CSJ0177-05-110
Proj IDNH 1402(089)
Work TypeLANDSCAPE DEVELOPMENT
 
0.0021838258.201818307.2598.9
Work Order11-03-14
Work Began01-14-15
Work Completed
Time Computed01-02-15
Contract Working Days90
Addl Days Granted0
Working Days Charged91
Percent Time Used101
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-05-110
G & A BORING (56.49)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.37)
Contract #08143233
Totals1838258.2054310.441818307.2598.9

CountyHARRIS
HighwayIH 69
FromLITTLE YORK ROAD
ToFM 1960
CSJ0177-07-112
Proj IDNH 1702(628)
Work TypeLANDSCAPING
 
16.785598752.6475424.7112.5
Work Order09-18-17
Work Began12-04-17
Work Completed
Time Computed10-18-17
Contract Working Days60
Addl Days Granted0
Working Days Charged20
Percent Time Used33
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-07-112
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173025
Totals598752.6437482.1875424.7112.5

CountyBRAZORIA
HighwaySH 35
FromAT INDUSTRIAL DR
To.
CSJ0178-02-088
Proj IDNH 2017(483)
Work TypeADD LEFT TURN LANE
 
0.278261915.90248558.0294.8
Work Order05-09-17
Work Began07-17-17
Work Completed
Time Computed07-08-17
Contract Working Days81
Addl Days Granted0
Working Days Charged35
Percent Time Used43
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0178-02-088
INTERSTATE BARRICADES & MARKINGS, INC. (2.06)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (5.72)
HIGHWAY 1, LLC (6.32)
QUALITY TURF FARMS, LC (3.68)
Contract #04173206
Totals261915.900.00248558.0294.8

CountyBRAZORIA
HighwaySH 35
FromAT JAMISON SLOUGH
ToAND AT OYSTER CREEK
CSJ0179-01-048
Proj IDSTP 1702(629)
Work TypeBR DECK REPLACEMENT
 
1.1992037263.05562472.6227.6
Work Order10-03-17
Work Began12-04-17
Work Completed
Time Computed12-02-17
Contract Working Days307
Addl Days Granted0
Working Days Charged34
Percent Time Used11
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0179-01-048
RAMPART HYDRO SERVICES (24.62)
PROFESSIONAL TRAFFIC CONTROL, LLC (2.18)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.12)
LONE STAR TRAFFIC SERVICE, INC. (0.56)
TLC TRUCKING & CONTRACTING, INC. (3.87)
Contract #08173024
Totals2037263.05269694.17562472.6227.6

CountyFORT BEND
HighwaySS 10
FromUS 59 SOUTH
ToSH 36
CSJ0187-05-048
Proj IDSTP 1602(587)MM
Work TypeGR, STRS, BASE & SURF
 
4.82511736891.3411351467.3696.7
Work Order09-15-16
Work Began09-26-16
Work Completed
Time Computed11-14-16
Contract Working Days219
Addl Days Granted0
Working Days Charged210
Percent Time Used95
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0187-05-048
SCOTT DERR PAINTING CO (0.00)
QUALITY TURF FARMS, LC (3.34)
MESA ROD BUSTERS, INC. (1.27)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.45)
WILLOW CITY SIGN & RAIL, INC. (0.72)
BATTERSON,LLP (1.90)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (13.32)
SHAW DRILLING, LLC (1.91)
Contract #08163006
Totals11736891.340.0011351467.3696.7

CountyFORT BEND
HighwaySH 36
FromSP 10
ToAUSTIN C/L
CSJ0187-05-060
Proj IDNH 1602(074)
Work TypeBASE REP AND OVERLAY
 
34.9794918131.865653270.9899.9
Work Order11-29-16
Work Began01-25-17
Work Completed
Time Computed01-28-17
Contract Working Days120
Addl Days Granted0
Working Days Charged99
Percent Time Used82
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0187-05-060
MARTIN ASPHALT COMPANY (1.02)
ROADSAFE TRAFFIC SYSTEMS, INC. (5.55)
THIRD COAST SERVICES LLC (0.31)
TROUT TRUCKING_COMPANY INC. (0.05)
WEST TEXAS RUMBLE STRIP (0.38)
Contract #05163013
Totals4918131.860.005653270.9899.9

CountyBRAZORIA
HighwaySH 35
FromSH 36
To17TH ST
CSJ0188-07-005
Proj IDCM 2016(268)
Work TypeCONSTRUCT SIDEWALKS
 
0.589741699.95660657.28100.0
Work Order05-09-16
Work Began07-12-16
Work Completed02-05-18
Time Computed07-08-16
Contract Working Days71
Addl Days Granted27
Working Days Charged173
Percent Time Used176
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0188-07-005
LONESTAR TRAFFIC SAFETY, LLC (0.46)
CENTEX HYDROSEED (1.75)
REPUBLIC TRAFFIC SAFETY, INC. (0.32)
Contract #11153011
Totals741699.950.00660657.28100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10