Monthly State Let Maintenance Report For Fort Worth District As Of Feb 09, 2018 Page 3 Of 4

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwaySH0114
FromVARIOUS ROADWAYS IN (TOLLROAD)
ToNORTH TARRANT COUNTY
CSJ6298-85-001
Proj IDRMC - 629885001
Work TypeROUTINE SWEEPING AND DEBRIS REMOVAL
 
0.010525027.00484178.0092.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-16-16
Work Began03-17-16
Work Completed
Time Computed03-16-16
Contract Working Days365
Addl Days Granted0
Working Days Charged338
Percent Time Used92
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6298-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164214
Totals525027.000.00484178.0092.2

CountyERATH
HighwayUS0067
FromVARIOUS LOCATIONS IN
ToERATH, HOOD AND SOMERVELL
CSJ6299-80-001
Proj IDRMC - 629980001
Work TypeFULL WIDTH MOWING
 
0.010308378.620.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12174008
Totals308378.620.000.000.0

CountyWISE
HighwayUS0380
FromVARIOUS ROADWAYS IN WISE AND JACK
ToCOUNTIES
CSJ6299-89-001
Proj IDRMC - 629989001
Work TypeTHERMOPLASTIC REFLECTORIZED PAVEMENT MRK
 
0.0101196127.191152485.28100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-20-16
Work Began06-20-16
Work Completed11-16-17
Time Computed06-23-16
Contract Working Days83
Addl Days Granted15
Working Days Charged94
Percent Time Used95
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164001
Totals1196127.190.001152485.28100.0

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6300-65-001
Proj IDRMC - 630065001
Work TypeKEENE FLEX PVMT REPAIR FY17
 
0.0101728825.001615127.4893.4
Work Order09-25-17
Work Began09-26-17
Work Completed
Time Computed09-26-17
Contract Working Days30
Addl Days Granted103
Working Days Charged57
Percent Time Used42
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174001
Totals1728825.00308612.211615127.4893.4

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6300-66-001
Proj IDRMC - 630066001
Work TypeFLEX PVMT STRUCTURE REPAIR
 
0.0102198000.003084975.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-03-16
Work Began00-00-00
Work Completed
Time Computed10-11-16
Contract Working Days75
Addl Days Granted0
Working Days Charged57
Percent Time Used76
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164002
Totals2198000.000.003084975.0099.9

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6300-82-001
Proj IDRMC - 630082001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010471125.00380108.0080.6
Work Order06-15-17
Work Began06-20-17
Work Completed
Time Computed06-20-17
Contract Working Days146
Addl Days Granted0
Working Days Charged84
Percent Time Used57
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-82-001
RAFTER JK CONSTRUCTION, LLC (100.00)
KASPARIAN UNDERGROUND, LLC (98.08)
BOEN LANDSCAPING & IRRIGATION, LLC (98.08)
Contract #08164203
Totals471125.000.00380108.0080.6

CountyJACK
HighwayFM2210
FromVARIOUS ROADWAYS IN
ToTHE FORT WORTH DISTRICT
CSJ6300-99-001
Proj IDRMC - 630099001
Work TypeSEAL COAT
 
0.0101471921.41363657.9224.7
Work Order00-00-00
Work Began05-02-17
Work Completed
Time Computed05-01-17
Contract Working Days16
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174001
Totals1471921.410.00363657.9224.7

CountyTARRANT
HighwaySH0199
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6301-08-001
Proj IDRMC - 630108001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010443500.00440753.5099.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-24-17
Work Began01-24-17
Work Completed
Time Computed01-31-17
Contract Working Days53
Addl Days Granted0
Working Days Charged51
Percent Time Used96
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164025
Totals443500.000.00440753.5099.3

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToPARKER & PALO PINTO COUNTIES
CSJ6301-25-001
Proj IDRMC - 630125001
Work TypeGUARDRAIL & CABLE BARRIER REPAIR
 
0.010672010.00531472.0079.0
Work Order10-18-16
Work Began10-26-16
Work Completed
Time Computed10-18-16
Contract Working Days365
Addl Days Granted134
Working Days Charged465
Percent Time Used93
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164002
Totals672010.0065197.00531472.0079.0

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN PARKER
ToAND PALO PINTO COUNTIES
CSJ6301-26-001
Proj IDRMC - 630126001
Work TypePARKER FLEX PVMT REPAIR
 
0.0101476158.001846760.3099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-16
Work Began09-20-16
Work Completed
Time Computed09-27-16
Contract Working Days36
Addl Days Granted0
Working Days Charged10
Percent Time Used27
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164001
Totals1476158.000.001846760.3099.9

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6301-47-001
Proj IDRMC - 630147001
Work TypeCLEANING & RESHAPING DITCHES
 
0.010419000.40356660.71100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-19-17
Work Began07-13-17
Work Completed12-19-17
Time Computed06-26-17
Contract Working Days80
Addl Days Granted0
Working Days Charged84
Percent Time Used105
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164026
Totals419000.400.00356660.71100.0

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN_JOHNSON,
ToHOOD, ERATH, AND SOMERVELL COUNTIES
CSJ6302-92-001
Proj IDRMC - 630292001
Work TypeCLEANING AND SEALING JOINTS & CRACKS
 
0.010323385.1225634.087.9
Work Order02-22-17
Work Began02-17-17
Work Completed
Time Computed02-16-17
Contract Working Days60
Addl Days Granted0
Working Days Charged39
Percent Time Used65
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164202
Totals323385.120.0025634.087.9

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6302-94-001
Proj IDRMC - 630294001
Work TypeCALL OUT REFLEC PAV MRKGS & MRKRS
 
0.010283423.72171429.7860.4
Work Order09-01-17
Work Began10-02-17
Work Completed
Time Computed10-02-17
Contract Working Days121
Addl Days Granted0
Working Days Charged19
Percent Time Used15
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164204
Totals283423.723943.90171429.7860.4

CountyTARRANT
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToTXDOT FORT WORTH DISTRICT
CSJ6305-39-001
Proj IDRMC - 630539001
Work TypeROADWAY SIGN MAINTENANCE
 
0.001462241.40233356.5050.4
Work Order04-13-17
Work Began07-02-17
Work Completed
Time Computed04-19-17
Contract Working Days365
Addl Days Granted0
Working Days Charged174
Percent Time Used47
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164206
Totals462241.4040622.00233356.5050.4

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS
ToWITHIN SOUTH TARRANT COUNTY
CSJ6306-60-001
Proj IDRMC - 630660001
Work TypeROUTINE SWEEPING & DEBRIS REMOVAL
 
0.010897886.54682960.4476.0
Work Order03-27-17
Work Began03-27-17
Work Completed
Time Computed04-03-17
Contract Working Days365
Addl Days Granted0
Working Days Charged311
Percent Time Used85
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6306-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164001
Totals897886.5467221.71682960.4476.0

CountyTARRANT
HighwayIH0020
FromVARIOUS BRIDGES IN THE
ToFORT WORTH DISTRICT
CSJ6307-51-001
Proj IDBPM - 630751001
Work TypeSTRUCTURAL BRIDGE REPAIR
 
0.010547186.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days214
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6307-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174216
Totals547186.000.000.000.0

CountyTARRANT
HighwaySH0114
FromVARIOUS ROADWAYS WITHIN
ToNORTH TARRANT COUNTY
CSJ6308-12-001
Proj IDRMC - 630812001
Work TypeREFLEC. PAV. MRKINGS & MRKS
 
0.0101148264.410.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6308-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174202
Totals1148264.410.000.000.0

CountyTARRANT
HighwayIH0035W
FromVARIOUS ROADWAYS
ToWITHIN SOUTH TARRANT COUNTY
CSJ6311-70-001
Proj IDRMC - 631170001
Work TypeGUARDRAIL INSTALLION AND REPAIR
 
0.0103056225.002849285.0093.2
Work Order03-27-17
Work Began03-27-17
Work Completed
Time Computed04-03-17
Contract Working Days365
Addl Days Granted0
Working Days Charged306
Percent Time Used83
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174001
Totals3056225.00285950.002849285.0093.2

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6313-33-001
Proj IDRMC - 631333001
Work TypeGUARDRAIL & MEDIAN CABLE REPAIR KEENE
 
0.010564100.00184390.0032.6
Work Order08-08-17
Work Began08-15-17
Work Completed
Time Computed08-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged166
Percent Time Used45
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-33-001
ONYX FARM CONSTRUCTION, LLC (28.65)
Contract #05174009
Totals564100.0019045.00184390.0032.6

CountyTARRANT
HighwaySH0114
FromVARIOUS ROADWAYS IN CONNECTOR (TOLLROAD)
ToNORTH TARRANT COUNTY
CSJ6313-45-001
Proj IDRMC - 631345001
Work TypeROUTINE SWEEPING AND DEBRIS REMOVAL
 
0.010468221.00192981.5041.2
Work Order07-07-17
Work Began07-14-17
Work Completed
Time Computed07-14-17
Contract Working Days365
Addl Days Granted0
Working Days Charged194
Percent Time Used53
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174209
Totals468221.0027310.50192981.5041.2

page 1 | page 2 | page 3 | page 4