Monthly State Let Maintenance Report For Corpus Christi District As Of Jan 10, 2018 Page 2 Of 2

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNUECES
HighwayIH0037
FromVARIOUS IN NUECES, JIM WELLS,
ToKLEBERG, & LIVE OAK COUNTIES
CSJ6313-14-001
Proj IDRMC - 631314001
Work TypeSTRIPING & PAVEMENT MARKINGS
 
0.9991906409.18740336.1738.8
Work Order04-20-17
Work Began00-00-00
Work Completed
Time Computed05-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged245
Percent Time Used33
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174212
Totals1906409.180.00740336.1738.8

CountySAN PATRICIO
HighwayUS0181
FromSAN PATRICIO, ARANSAS, REFUGIO, BEE,
ToGOLIAD & KARNES COUNTIES
CSJ6313-15-001
Proj IDRMC - 631315001
Work TypeSTRIPING & PAVEMENT MARKINGS
 
0.9991885781.50483893.1525.6
Work Order04-17-17
Work Began00-00-00
Work Completed
Time Computed05-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged243
Percent Time Used33
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174213
Totals1885781.500.00483893.1525.6

CountyNUECES
HighwaySH0358
FromVARIOUS
To.
CSJ6313-60-001
Proj IDRMC - 631360001
Work TypeNOVACHIP
 
999.9902081077.972516769.8399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted53
Working Days Charged175
Percent Time Used41
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174208
Totals2081077.970.002516769.8399.9

CountySAN PATRICIO
HighwaySH0359
FromVARIOUS
To.
CSJ6314-04-001
Proj IDRMC - 631404001
Work TypeMILL & OVERLAY
 
1.5622243158.387116132.4499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6314-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174007
Totals2243158.38767266.977116132.4499.9

CountyKARNES
HighwayFM0626
FromVARIOUS
To.
CSJ6315-62-001
Proj IDRMC - 631562001
Work TypeCULVERT REPLACEMENT
 
0.999483707.97257623.0653.8
Work Order09-13-17
Work Began00-00-00
Work Completed
Time Computed09-21-17
Contract Working Days37
Addl Days Granted0
Working Days Charged42
Percent Time Used113
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174007
Totals483707.9774348.11257623.0653.8

CountyNUECES
HighwayUS0077
FromVARIOUS HIGHWAYS CC DISTRICT
ToVARIOUS HIGHWAYS CC DISTRICT
CSJ6316-28-001
Proj IDRMC - 631628001
Work TypeDEBRIS REMOVAL AND DISPOSAL
 
0.001900100.002697977.5899.9
Work Order06-01-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days40
Addl Days Granted80
Working Days Charged82
Percent Time Used68
Contractor(s)
T.F.R. ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174215
Totals900100.00115328.502697977.5899.9

CountyNUECES
HighwayIH0037
FromVARIOUS
To.
CSJ6318-80-001
Proj IDRMC - 631880001
Work TypeCLEANING, SWEEPING & DEBRIS REMOVAL
 
62.4401603286.66403000.8625.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174215
Totals1603286.6695815.95403000.8625.1

CountySAN PATRICIO
HighwayFM0796
FromVARIOUS
To.
CSJ6319-23-001
Proj IDRMC - 631923001
Work TypeCONCRETE RIPRAP REPAIR & DITCH CLEANING
 
0.999457753.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged4
Percent Time Used1
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6319-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174008
Totals457753.320.000.000.0

CountyNUECES
HighwaySH0361
FromAT PORT ARANSAS
To.
CSJ6319-80-001
Proj IDRMC - 631980001
Work TypeDRY DOCKING 28-CAR FERRY AT PORT ARANSAS
 
0.9993824363.0015440.000.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
SOUTHWEST SHIPYARD, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6319-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174016
Totals3824363.0015440.0015440.000.4