Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | WHEELER |
Highway | US 83 |
From | @ SWEETWATER CREEK |
To | . |
CSJ | 0030-08-038 |
Proj ID | BR 2023(936) |
Work Type | BRIDGE REPLACEMENT |
|
| | 5746110.50 | | 1601609.96 | 27.8 |
County | WHEELER |
Highway | FM 2473 |
From | @ NORTH FORK RED RIVER |
To | . |
CSJ | 2051-01-013 |
Proj ID | BR 2023(936) |
Work Type | BRIDGE REPLACEMENT |
|
| | 8517304.00 | | 634392.00 | 7.4 |
Work Order | 08-03-23 |
Work Began | 03-11-24 |
Work Completed | |
Time Computed | 09-03-23 |
Contract Working Days | 354 |
Addl Days Granted | 0 |
Working Days Charged | 35 |
Percent Time Used | 9 |
Contractor(s) |
EARTH BUILDERS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0030-08-038 MORRIS COUNTY CONTRACTORS, L.L.C. (0.60) FC TRAFFIC CONTROL, INC. (0.19) JB PINNACLE GROUP, LLC (1.76) LANCO TURF & SEEDING, INC. (0.02) M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.76) PRIMATE CONSTRUCTION, LP (0.14) TRP CONSTRUCTION GROUP, LLC (0.77) JVH4 SERVICES, LLC (0.18) TORO BRAVO CONSTRUCTION, LLC (0.32) TORO BRAVO CONSTRUCTION, LLC (0.62)
|
Contract # | 06233606 |
| Totals | 14263414.50 | 1238154.00 | 2236001.96 | 15.6 |
|
County | WHEELER |
Highway | US 83 |
From | CR 15, SOUTH |
To | COLLINGSWORTH C/L |
CSJ | 0031-01-022 |
Proj ID | F 2023(283) |
Work Type | SUPER-2 HIGHWAY |
|
| | 2011072.01 | | 2010127.63 | 99.9 |
County | COLLINGSWORTH |
Highway | US 83 |
From | WHEELER C/L, SOUTH |
To | 7.551 MILES |
CSJ | 0031-02-029 |
Proj ID | F 2023(283) |
Work Type | SUPER-2 HIGHWAY |
|
| | 6427152.76 | | 6081011.73 | 94.6 |
County | COLLINGSWORTH |
Highway | US 83 |
From | 7.551 MILES SOUTH OF WHEELER C/L, S |
To | FM 1439 |
CSJ | 0031-03-044 |
Proj ID | F 2023(283) |
Work Type | SUPER-2 HIGHWAY |
|
| | 3753664.45 | | 3798894.81 | 99.9 |
Work Order | 01-12-23 |
Work Began | 03-13-23 |
Work Completed | |
Time Computed | 03-13-23 |
Contract Working Days | 237 |
Addl Days Granted | 2 |
Working Days Charged | 169 |
Percent Time Used | 71 |
Contractor(s) |
DUININCK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0031-01-022 FC TRAFFIC CONTROL, INC. (0.40) H & F TRUCKING (0.41) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.21) HJC FARMS, INC. (1.87) JENNINGS TRUCKING SERVICE, INC. (0.41) SURFACE PREPARATION TECHNOLOGIES, LLC (0.22) TEXAS PANHANDLE CONSTRUCTION, INC. (1.06) TEXOP CONSTRUCTION (0.56) WEST INFRASTRUCTURE CONSTRUCTION, LLC (0.24) MOBILE ENTERPRISES, INC. (0.11) RILEY INDUSTRIAL SERVICES, INC. (0.40)
|
Contract # | 12223209 |
| Totals | 12191889.22 | 415971.73 | 11890034.17 | 97.5 |
|
County | DONLEY |
Highway | US 287 |
From | ARMSTRONG C/L, EAST |
To | CLARENDON ECL (SBL) |
CSJ | 0042-06-076 |
Proj ID | F 2024(069) |
Work Type | OVERLAY |
|
| | 6446300.55 | | 1458312.14 | 22.6 |
Work Order | 10-23-23 |
Work Began | 04-22-24 |
Work Completed | |
Time Computed | 10-23-23 |
Contract Working Days | 95 |
Addl Days Granted | 0 |
Working Days Charged | 7 |
Percent Time Used | 7 |
Contractor(s) |
J. LEE MILLIGAN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0042-06-076 TRP CONSTRUCTION GROUP, LLC (2.92) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.24) BARRICADES UNLIMITED (0.45) SURFACE PREPARATION TECHNOLOGIES, LLC (0.33)
|
Contract # | 09233036 |
| Totals | 6446300.55 | 1384986.14 | 1458312.14 | 22.6 |
|
County | DONLEY |
Highway | US 287 |
From | SOUTH THURMAN STREET, EAST |
To | FM 1260 |
CSJ | 0042-07-071 |
Proj ID | STP 2B24(018)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 576583.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 48 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MASSANA CONSTRUCTION INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0042-07-071 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 05243242 |
| Totals | 576583.00 | 0.00 | 0.00 | 0.0 |
|
County | HALL |
Highway | US 287 |
From | 348' SOUTH OF 2ND STREET, SOUTH |
To | 1.718 MILES |
CSJ | 0042-09-124 |
Proj ID | C 42-9-124 |
Work Type | NEW LOCATION FREEWAY |
|
| | 13478722.75 | | 14867047.49 | 99.9 |
Work Order | 06-22-21 |
Work Began | 08-17-21 |
Work Completed | |
Time Computed | 06-22-21 |
Contract Working Days | 420 |
Addl Days Granted | 53 |
Working Days Charged | 481 |
Percent Time Used | 101 |
Contractor(s) |
CK NEWBERRY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0042-09-124 BARRICADES UNLIMITED (0.98) J. H. ODEN CONTRACTING COMPANY (0.82) M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.60) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36) URBAN INFRACONSTRUCTION LLC (3.99) WEST TEXAS ROCK RESOURCES, LLC (0.02) WILLIS ELECTRIC CO., LP (0.89) HOLMES CONSTRUCTION CO., L.P. (0.41) WILLIAMS ROAD, LLC (0.11) B&B TRUCKING (0.44) HODGES AND SON CONSTRUCTION COMPANY, INC. (1.78) TORO BRAVO CONSTRUCTION, LLC (0.08) TORO BRAVO CONSTRUCTION, LLC (0.37) MCINTOSH FLOW SERVICE LLC (0.07) PANHANDLE SWEEPING & MAINTENANCE, LLC (0.02) A.W. THEIS (0.07) FUQUAY, INC. (7.35) TEXAS GUARDRAIL CONTRACTORS LLC (0.27) POPWELL, INC (0.14) PINNACLE GRINDING AND GROOVING LLC (0.06) STRAIGHT LINE SAWING & SEALING, INC. (0.03) TRP CONSTRUCTION GROUP, LLC (0.55) RK HALL, LLC (13.85) GARY A. CRAIN, INC. (0.03)
|
Contract # | 05213206 |
| Totals | 13478722.75 | 0.00 | 14867047.49 | 99.9 |
|
County | CHILDRESS |
Highway | US 287 |
From | 2732' W OF FM 164 (NBL & SBL) (RAMPS), E |
To | CHILDRESS WCL |
CSJ | 0042-12-086 |
Proj ID | F 2024(640) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| | 15308760.06 | | 2122507.60 | 13.8 |
Work Order | 03-14-24 |
Work Began | 04-22-24 |
Work Completed | |
Time Computed | 03-14-24 |
Contract Working Days | 159 |
Addl Days Granted | 0 |
Working Days Charged | 8 |
Percent Time Used | 5 |
Contractor(s) |
GILVIN-TERRILL, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-086 ALAMO BROTHERS CONCRETE INC (1.52) DUSTIN ALLEN, INC. (1.34) TRP CONSTRUCTION GROUP, LLC (0.77) BARRICADES UNLIMITED (0.15) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.05) H & F TRUCKING (3.59) A BROTHERS MILLING, LLC (0.82) LMSE TRUCKING, LLC (4.59)
|
Contract # | 02243212 |
| Totals | 15308760.06 | 1913707.60 | 2122507.60 | 13.8 |
|
County | CHILDRESS |
Highway | US 287 |
From | 335' EAST OF FM 2530, EAST |
To | HARDEMAN C/L (NBL) |
CSJ | 0043-01-083 |
Proj ID | BR 2023(360) |
Work Type | OVERLAY |
|
| | 6175663.87 | | 6790599.46 | 99.9 |
Work Order | 01-04-23 |
Work Began | 04-05-23 |
Work Completed | |
Time Computed | 01-04-23 |
Contract Working Days | 62 |
Addl Days Granted | 60 |
Working Days Charged | 135 |
Percent Time Used | 110 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-083 FC TRAFFIC CONTROL, INC. (0.40) TEXOP CONSTRUCTION (0.89) ALAMO BROTHERS CONCRETE INC (1.90) HJC FARMS, INC. (5.85) TEXAS PANHANDLE CONSTRUCTION, INC. (1.78) SURFACE PREPARATION TECHNOLOGIES, LLC (0.28) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.24)
|
Contract # | 12223035 |
| Totals | 6175663.87 | 508500.91 | 6790599.46 | 99.9 |
|
County | HARDEMAN |
Highway | US 287 |
From | 65' WEST OF FM 2568, EAST |
To | WILBARGER C/L |
CSJ | 0043-04-083 |
Proj ID | F 2024(638) |
Work Type | OVERLAY |
|
| | 8059390.88 | | 1135545.95 | 14.0 |
Work Order | 02-02-24 |
Work Began | 04-29-24 |
Work Completed | |
Time Computed | 02-02-24 |
Contract Working Days | 79 |
Addl Days Granted | 5 |
Working Days Charged | 2 |
Percent Time Used | 2 |
Contractor(s) |
DUININCK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0043-04-083 A BROTHERS MILLING, LLC (0.41) DUSTIN ALLEN, INC. (1.37) FC TRAFFIC CONTROL, INC. (0.40) JENNINGS TRUCKING SERVICE, INC. (0.55) TRP CONSTRUCTION GROUP, LLC (2.12) MOBILE ENTERPRISES, INC. (1.10) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.56) SURFACE PREPARATION TECHNOLOGIES, LLC (0.24) W. S. CONSTRUCTION COMPANY (0.43)
|
Contract # | 01243211 |
| Totals | 8059390.88 | 794388.94 | 1135545.95 | 14.0 |
|
County | HARDEMAN |
Highway | SS 133 |
From | @ LP 285 |
To | . |
CSJ | 0043-10-007 |
Proj ID | STP 2023(825)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 34272.00 | | 34172.00 | 99.7 |
County | HARDEMAN |
Highway | SL 285 |
From | @ DRAW |
To | . |
CSJ | 0043-23-008 |
Proj ID | BR 2023(824) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.035 | 1836659.00 | | 1833872.00 | 99.8 |
Work Order | 07-19-23 |
Work Began | 08-21-23 |
Work Completed | |
Time Computed | 07-19-23 |
Contract Working Days | 134 |
Addl Days Granted | 0 |
Working Days Charged | 133 |
Percent Time Used | 99 |
Contractor(s) |
HODGES AND SON CONSTRUCTION COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0043-10-007 FC TRAFFIC CONTROL, INC. (0.54) TORO BRAVO CONSTRUCTION, LLC (0.75) MORRIS COUNTY CONTRACTORS, L.L.C. (1.51) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.90) HOUSTON SAWING & DRILLING (0.41)
|
Contract # | 06233028 |
| Totals | 1870931.00 | 20072.00 | 1868044.00 | 99.8 |
|
County | HALL |
Highway | SH 86 |
From | INTERSECTION OF SH 70, NORTH |
To | FM 657 |
CSJ | 0105-02-023 |
Proj ID | BR 2024(528) |
Work Type | OVERLAY |
|
| 8.270 | 6392222.95 | | 564821.20 | 8.8 |
County | HALL |
Highway | SH 70 |
From | TURKEY NCL, NORTH |
To | INTERSECTION OF SH 86 |
CSJ | 0105-02-026 |
Proj ID | F 2024(410) |
Work Type | OVERLAY |
|
| | 247566.55 | | 0.00 | 0.0 |
Work Order | 11-16-23 |
Work Began | 03-18-24 |
Work Completed | |
Time Computed | 11-16-23 |
Contract Working Days | 89 |
Addl Days Granted | 0 |
Working Days Charged | 17 |
Percent Time Used | 19 |
Contractor(s) |
J. LEE MILLIGAN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0105-02-023 SURFACE PREPARATION TECHNOLOGIES, LLC (0.35) BARRICADES UNLIMITED (0.56) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.28) TRP CONSTRUCTION GROUP, LLC (2.19)
|
Contract # | 10233029 |
| Totals | 6639789.50 | 109328.00 | 564821.20 | 8.5 |
|
County | DICKENS |
Highway | US 82 |
From | 1186' EAST OF DICKENS ECL, EAST |
To | 8.23 MILES (WBL) |
CSJ | 0132-01-055 |
Proj ID | C 132-1-55 |
Work Type | OVERLAY |
|
| | 11319017.73 | | 0.00 | 0.0 |
Work Order | 01-11-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 01-11-24 |
Contract Working Days | 99 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0132-01-055 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12233009 |
| Totals | 11319017.73 | 0.00 | 0.00 | 0.0 |
|
County | KING |
Highway | US 82 |
From | 0.5 MILES WEST OF SH 222, EAST |
To | KNOX C/L |
CSJ | 0133-01-049 |
Proj ID | F 2022(352) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| | 5768975.82 | | 6429583.86 | 99.9 |
Work Order | 02-16-22 |
Work Began | 09-30-22 |
Work Completed | |
Time Computed | 02-16-22 |
Contract Working Days | 141 |
Addl Days Granted | 3 |
Working Days Charged | 184 |
Percent Time Used | 127 |
Contractor(s) |
A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0133-01-049 STRIPING TECHNOLOGY, L.P. (3.44) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.18) WEST TEXAS ROCK RESOURCES, LLC (0.16) CONTRACTORS SERVICE, LTD. (0.42)
|
Contract # | 01223042 |
| Totals | 5768975.82 | 10260.00 | 6429583.86 | 99.9 |
|
County | WHEELER |
Highway | IH 40 |
From | GRAY C/L, EAST |
To | US 83 |
CSJ | 0275-12-085 |
Proj ID | F 2024(846) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 3449940.40 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 193 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
3LW CIVIL LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0275-12-085 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04243026 |
| Totals | 3449940.40 | 0.00 | 0.00 | 0.0 |
|
County | HALL |
Highway | SH 70 |
From | @ MULBERRY CREEK |
To | . |
CSJ | 0311-02-033 |
Proj ID | BR 2023(938) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.191 | 9334727.25 | | 5265671.88 | 56.4 |
Work Order | 07-26-23 |
Work Began | 11-08-23 |
Work Completed | |
Time Computed | 07-26-23 |
Contract Working Days | 468 |
Addl Days Granted | 0 |
Working Days Charged | 85 |
Percent Time Used | 18 |
Contractor(s) |
EARTH BUILDERS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0311-02-033 JB PINNACLE GROUP, LLC (1.60) M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.05) PENHALL COMPANY (0.15) TRP CONSTRUCTION GROUP, LLC (0.82) FC TRAFFIC CONTROL, INC. (0.19) LANCO TURF & SEEDING, INC. (0.46) MORRIS COUNTY CONTRACTORS, L.L.C. (0.53) TORO BRAVO CONSTRUCTION, LLC (0.22) TORO BRAVO CONSTRUCTION, LLC (0.42)
|
Contract # | 06233609 |
| Totals | 9334727.25 | 245740.00 | 5265671.88 | 56.4 |
|
County | CHILDRESS |
Highway | US 62 |
From | @ BUCK CREEK |
To | . |
CSJ | 0381-01-017 |
Proj ID | BR 2024(641) |
Work Type | BRIDGE REPLACEMENT |
|
| | 6310485.59 | | 0.00 | 0.0 |
Work Order | 03-14-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 03-14-24 |
Contract Working Days | 249 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ALTUS CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0381-01-017 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02243010 |
| Totals | 6310485.59 | 0.00 | 0.00 | 0.0 |
|
County | COLLINGSWORTH |
Highway | FM 338 |
From | US 83, EAST |
To | CR Z |
CSJ | 0449-01-022 |
Proj ID | C 449-1-22 |
Work Type | WIDEN NON-FREEWAY |
|
| | 4582258.60 | | 2311581.65 | 50.4 |
County | COLLINGSWORTH |
Highway | FM 338 |
From | CR Z, EAST |
To | CR 270 |
CSJ | 0449-01-023 |
Proj ID | F 2023(686) |
Work Type | WIDEN NON-FREEWAY |
|
| | 2540318.00 | | 1680760.68 | 66.1 |
Work Order | 06-14-23 |
Work Began | 08-01-23 |
Work Completed | |
Time Computed | 07-14-23 |
Contract Working Days | 182 |
Addl Days Granted | 3 |
Working Days Charged | 121 |
Percent Time Used | 65 |
Contractor(s) |
J. LEE MILLIGAN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0449-01-022 TRP CONSTRUCTION GROUP, LLC (2.20) HJC FARMS, INC. (4.26) SURFACE PREPARATION TECHNOLOGIES, LLC (0.30) FC TRAFFIC CONTROL, INC. (0.37) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.30) H & F TRUCKING (4.01)
|
Contract # | 05233212 |
| Totals | 7122576.60 | 25000.00 | 3992342.33 | 56.0 |
|
County | COLLINGSWORTH |
Highway | FM 338 |
From | CR 270, EAST |
To | OKLAHOMA STATE LINE |
CSJ | 0449-01-024 |
Proj ID | STP 2024(639)HES |
Work Type | WIDEN NON-FREEWAY |
|
| | 4695146.20 | | 0.00 | 0.0 |
Work Order | 03-21-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 03-21-24 |
Contract Working Days | 109 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
J. LEE MILLIGAN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0449-01-024 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02243024 |
| Totals | 4695146.20 | 0.00 | 0.00 | 0.0 |
|
County | KNOX |
Highway | FM 267 |
From | US 82, SOUTH |
To | SH 222 |
CSJ | 0538-01-027 |
Proj ID | STP 2023(580)HES |
Work Type | WIDEN NON-FREEWAY |
|
| | 6913833.35 | | 966865.50 | 13.9 |
Work Order | 05-17-23 |
Work Began | 07-17-23 |
Work Completed | |
Time Computed | 05-17-23 |
Contract Working Days | 177 |
Addl Days Granted | 0 |
Working Days Charged | 82 |
Percent Time Used | 46 |
Contractor(s) |
A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0538-01-027 CONTRACTORS SERVICE, LTD. (0.48) DUSTIN ALLEN, INC. (0.59) LINEAR TRAFFIC MARKINGS LLC (1.24) WEST TEXAS ROCK RESOURCES, LLC (0.24) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.42) W. S. CONSTRUCTION COMPANY (5.35)
|
Contract # | 04233016 |
| Totals | 6913833.35 | 45530.50 | 966865.50 | 13.9 |
|
County | BRISCOE ETC |
Highway | SH 256 ETC |
From | SH 86, EAST |
To | 10 MILES |
CSJ | 0541-01-033 |
Proj ID | F 2024(074) |
Work Type | SEAL COAT |
|
| | 7556670.11 | | 1489910.75 | 19.7 |
Work Order | 11-16-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 11-16-23 |
Contract Working Days | 57 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MISSOURI PETROLEUM PRODUCTS COMPANY LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0541-01-033 BARRICADES PLUS, LLC (1.36) CENTERLINE TECHNOLOGIES, LLC (3.46)
|
Contract # | 10233208 |
| Totals | 7556670.11 | 160015.00 | 1489910.75 | 19.7 |
|
County | CHILDRESS |
Highway | FM 268 |
From | US 287, EAST |
To | FM 1033 |
CSJ | 0704-02-022 |
Proj ID | BR 2022(505) |
Work Type | WIDEN NON-FREEWAY |
|
| | 8319405.00 | | 8200537.89 | 98.5 |
County | HARDEMAN |
Highway | FM 268 |
From | CHILDRESS C/L, SOUTH |
To | US 287 |
CSJ | 2533-01-015 |
Proj ID | BR 2022(505) |
Work Type | WIDEN NON-FREEWAY |
|
| | 6372293.34 | | 4295020.59 | 67.4 |
County | CHILDRESS |
Highway | FM 268 |
From | FM 1033, EAST |
To | HARDEMAN C/L |
CSJ | 2533-02-008 |
Proj ID | F 2022(507) |
Work Type | WIDEN NON-FREEWAY |
|
| | 2490642.56 | | 1799392.23 | 72.2 |
Work Order | 09-15-22 |
Work Began | 10-17-22 |
Work Completed | |
Time Computed | 09-15-22 |
Contract Working Days | 443 |
Addl Days Granted | 41 |
Working Days Charged | 297 |
Percent Time Used | 61 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0704-02-022 FC TRAFFIC CONTROL, INC. (0.22) TEXOP CONSTRUCTION (0.68) COPPELL CONSTRUCTION CO., INC. (11.10) BAHENA CONSTRUCTION CO.,INC. (20.81) WILLIS ELECTRIC CO., LP (0.92) MARCOM ENGINEERING COMPANY (0.29) TEXAS PANHANDLE CONSTRUCTION, INC. (0.70) SURFACE PREPARATION TECHNOLOGIES, LLC (0.21) WOLFE CONSTRUCTION GROUP, INCORPORATED (0.47) DUSTIN ALLEN, INC. (1.89) M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.86) TORO BRAVO CONSTRUCTION, LLC (0.06) FIBERTEX, LLC (0.02) A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.06)
|
Contract # | 08223261 |
| Totals | 17182340.90 | 3060501.18 | 14294950.71 | 83.1 |
|