Monthly State Let Construction Report For Abilene District As Of Oct 16, 2017 Page 1 Of 2

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayIH 20
FromMARTIN COUNTY LINE
ToNEAR US 87_(EB LANES ONLY)
CSJ0005-05-110
Proj IDNH 2017(833)
Work TypeOVERLAY
 
9.5205321335.32572343.3210.7
Work Order04-12-17
Work Began09-13-17
Work Completed
Time Computed06-12-17
Contract Working Days89
Addl Days Granted0
Working Days Charged61
Percent Time Used68
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-110
TOTAL HIGHWAY MAINTENANCE, LLC (0.40)
BARRICADES UNLIMITED (0.76)
TEX OP CONSTRUCTION, LP (2.55)
HJC FARMS, INC. (6.77)
DOUBLE A CONTRACTING, L.P. (0.25)
Contract #03173021
Totals5321335.32325862.50572343.3210.7

CountyHOWARD
HighwayIH 20
FromIH 20 AND MOORE FIELD ROAD
ToIH 20 AND MORE FIELD ROAD
CSJ0005-05-112
Proj IDBR 1702(476)
Work TypeINSTALL CRASHWALLS
 
1.0047767027.740.000.0
Work Order08-08-17
Work Began10-16-17
Work Completed
Time Computed09-07-17
Contract Working Days309
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-112
CONTRACTORS SERVICE COMPANY (1.06)
DIIBS SPECIALISTS (0.66)
DOUBLE A CONTRACTING, L.P. (3.12)
GIBSON & ASSOCIATES, INC. (0.47)
MCL CONTRACTING, LLC (1.60)
NELSON INDUSTRIAL SERVICES, INC. (0.08)
PRICE CONSTRUCTION, LTD. (1.34)
S & S BRIDGE PAINTING, INC. (7.03)
TEXAS CURB CUT, LP (0.04)
Contract #07173231
Totals7767027.740.000.000.0

CountyHOWARD
HighwayIH 20
FromIH 20 WEST BOUND AT UNION PAC RR
ToIH 20 WEST BOUND AT UNION PAC RR
CSJ0005-06-117
Proj IDBR 1702(598)
Work TypeBRIDGE REHAB
 
0.2401316919.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days99
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRUCTURAL TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-117
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173037
Totals1316919.240.000.000.0

CountyHOWARD
HighwayIH 20
FromN SCURRY ST
ToMOSS LAKE RD
CSJ0005-06-119
Proj IDSTP 1702(599)HES
Work TypeINSTALL MEDIAN BARRIER
 
11.6611664669.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-28-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days93
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-119
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173040
Totals1664669.160.000.000.0

CountyMITCHELL
HighwayBI 20-J
FromIH 20 W OF COLORADO CITY
ToIH 20 E OF COLORADO CITY
CSJ0005-12-013
Proj IDSTP 2017(455)
Work TypeFLX PAV STR RPR,UNDSL,&ACP OVERLAY
 
5.9262838058.332491214.4288.3
Work Order02-13-17
Work Began05-31-17
Work Completed
Time Computed05-15-17
Contract Working Days56
Addl Days Granted0
Working Days Charged77
Percent Time Used137
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-12-013
CONTRACTORS SERVICE COMPANY (0.41)
HUDSON, INC. (2.23)
MPB, INC. (2.13)
BARRICADES UNLIMITED (3.59)
Contract #01173207
Totals2838058.33591631.472491214.4288.3

CountyNOLAN
HighwayIH 20
FromEAST BI 20-M IN SWEETWATER
ToTAYLOR COUNTY LINE
CSJ0006-03-132
Proj IDNH 2017(456)
Work TypeMILL,SPOT REPAIR,UNDERSEAL &OVERLAY
 
12.47714579827.285280134.5136.2
Work Order05-09-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days331
Addl Days Granted0
Working Days Charged50
Percent Time Used15
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-03-132
CONTRACTORS SERVICE COMPANY (0.68)
WEST TEXAS RUMBLE STRIP (0.20)
AARON"S CONCRETE SAWING AND SEALING INC. (0.54)
DOUBLE A CONTRACTING, L.P. (1.65)
DUSTROL, INC. (1.53)
RPV CONSTRUCTION (2.93)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.35)
CHEROKEE SERVICES (0.86)
HJC FARMS, INC. (3.21)
SCR CONSTRUCTION CO., INC. (1.35)
TITAN MILLING INC. (0.99)
Contract #03173237
Totals14579827.282086395.395280134.5136.2

CountyTAYLOR ETC
HighwayIH 20 ETC
FromNOLAN COUNTY LINE
ToAPPROX 270' EAST OF CR 287
CSJ0006-04-079
Proj IDNH 2017(931)
Work TypeINSTALL PAVEMENT MARKINGS
 
255.8671158772.031022253.6288.2
Work Order05-11-17
Work Began06-26-17
Work Completed
Time Computed06-12-17
Contract Working Days80
Addl Days Granted0
Working Days Charged67
Percent Time Used83
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0006-04-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173026
Totals1158772.0352816.351022253.6288.2

CountyTAYLOR
HighwayIH 20
FromIH 20 EAST BOUND LANE
ToAT SH 351(AMBLER AVE IN ABILENE)
CSJ0006-06-099
Proj IDBR 1602(557)
Work TypeREPLACE BRIDGE AND APPROACHES
 
3.93212169359.958492644.7469.7
CountyTAYLOR
HighwaySH 351
FromEAST STAMFORD STREET
ToEAST OVERLAND STREET
CSJ0011-01-035
Proj IDNH 1602(559)
Work TypeEXC,EMB, CONC PAV
 
0.1802469640.051343658.5654.4
Work Order11-29-16
Work Began03-20-17
Work Completed
Time Computed12-29-16
Contract Working Days445
Addl Days Granted0
Working Days Charged142
Percent Time Used31
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-06-099
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
DUSTIN ALLEN, INC. (1.19)
A BROTHERS MILLING, LLC (0.69)
STRIPE-A-ZONE, INC. (2.11)
NOBLES ROAD CONSTRUCTION, INC. (23.37)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.85)
WILLIS ELECTRIC CO., LP (2.41)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.88)
MCL CONTRACTING, LLC (0.09)
MCL CONTRACTING, LLC (0.83)
BRENDA CONSTRUCTION (4.15)
UNDER CONSTRUCTION INC. (0.31)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.08)
Contract #10163008
Totals14639000.001555473.509836303.3067.1

CountyTAYLOR
HighwayIH 20
FromAT FW&D (SOUTHERN SWITCHING) RR
ToHARDY STREET WEST BOUND
CSJ0006-06-103
Proj IDBR 1702(237)
Work TypeREHAB EXISTING BRIDGE
 
0.6372981256.75415166.2513.9
Work Order07-31-17
Work Began09-11-17
Work Completed
Time Computed08-30-17
Contract Working Days166
Addl Days Granted0
Working Days Charged12
Percent Time Used7
Contractor(s)
JAY-REESE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-06-103
AREA WIDE PROTECTIVE, INC. (3.46)
TEXOP CONSTRUCTION (0.29)
S & S BRIDGE PAINTING, INC. (10.71)
WILLIS ELECTRIC CO., LP (0.59)
NOBLES ROAD CONSTRUCTION, INC. (3.53)
AARON CONCRETE CONTRACTORS, L.P. (3.75)
12-1 HIGHWAY AND ENVIRONMENTAL SERVICES, LLC (1.46)
STRIPE-A-ZONE, INC. (1.84)
ALTUS TRAFFIC MANAGEMENT LLC (0.34)
Contract #06173039
Totals2981256.75415166.25415166.2513.9

CountyNOLAN ETC
HighwayBI 20-L ETC
From0.8 MILE NORTH OF IH 20
To1.2 MILES NORTH OF IH 20
CSJ0006-14-004
Proj IDSTP 2017(834)HES
Work TypeSURFACE TREAT AND INSTALL CHEVRONS
 
23.2231848432.22521339.0228.2
Work Order05-18-17
Work Began09-20-17
Work Completed
Time Computed08-16-17
Contract Working Days90
Addl Days Granted0
Working Days Charged19
Percent Time Used21
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-14-004
WILLIS ELECTRIC CO., LP (33.43)
HJC FARMS, INC. (15.61)
Contract #03173026
Totals1848432.22521339.02521339.0228.2

CountyCALLAHAN
HighwayIH 20
FromNEAR BAIRD WEST CITY LIMIT_(WBL)
ToAPPROX 0.3 MI E OF MEXIA CREEK
CSJ0007-01-054
Proj IDNH 2017(855)
Work TypeOVERLAY
 
17.5828248492.442962048.1535.9
Work Order05-18-17
Work Began07-17-17
Work Completed
Time Computed07-17-17
Contract Working Days303
Addl Days Granted0
Working Days Charged41
Percent Time Used13
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-01-054
DOUBLE A CONTRACTING, L.P. (0.28)
CONTRACTORS SERVICE COMPANY (0.28)
SCR CONSTRUCTION CO., INC. (0.84)
TOTAL HIGHWAY MAINTENANCE, LLC (1.05)
A BROTHERS MILLING, LLC (2.59)
HJC FARMS, INC. (7.44)
Contract #04173009
Totals8248492.44711944.002962048.1535.9

CountyCALLAHAN ETC
HighwayIH 20 ETC
From640' E. OF FM 2047 (FRTG RDS ONLY)
To1700' E. OF MEXIA CRK BRIDGE
CSJ0007-01-056
Proj IDNH 2017(364)
Work TypeSEAL COAT
 
245.9788458527.238143095.8396.2
Work Order01-25-17
Work Began05-02-17
Work Completed
Time Computed05-02-17
Contract Working Days70
Addl Days Granted0
Working Days Charged64
Percent Time Used91
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-01-056
FLATE LINE, INC. (4.70)
RED 16 CONSTRUCTION (0.86)
Contract #12163005
Totals8458527.2314284.558143095.8396.2

CountyTAYLOR
HighwaySH 351
FromIH 20
ToABILENE EAST CITY LIMIT
CSJ0011-01-030
Proj IDSTP 1302(056)
Work TypeFL BS,STRS,PCTB,C&G,SDWLK,DRVWY,SMA
 
1.7686920469.817567024.32100.0
Work Order04-10-15
Work Began06-10-15
Work Completed09-29-17
Time Computed06-10-15
Contract Working Days270
Addl Days Granted77
Working Days Charged326
Percent Time Used93
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-030
CONTRACTORS SERVICE COMPANY (0.59)
WILLIS ELECTRIC CO., LP (12.40)
STRIPING TECHNOLOGY, L.P. (1.68)
MARCOM"S MOWING SERVICE, LLC (0.26)
O. TREVINO CONSTRUCTION, LLC (5.52)
WOLFE CONSTRUCTION GROUP, INC. (0.91)
BILL STARKS CONSTRUCTION COMPANY (3.42)
JORDAN CONCRETE (13.77)
GONZALES CONCRETE CONTRACTORS, INC. (6.30)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (0.66)
Contract #03153036
Totals6920469.8159110.507567024.32100.0

CountySHACKELFORD ETC
HighwayUS 180 ETC
From@ US 283
To.
CSJ0011-06-045
Proj IDSTP 1602(560)HES
Work TypeFLASH BEACON
 
2.390467417.10399392.1088.2
Work Order09-15-16
Work Began01-10-17
Work Completed
Time Computed12-14-16
Contract Working Days87
Addl Days Granted0
Working Days Charged109
Percent Time Used125
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-06-045
TOTAL HIGHWAY MAINTENANCE, LLC (2.01)
COLLIER DIRECTIONAL DRILLING (8.62)
Contract #08163239
Totals467417.10101890.84399392.1088.2

CountyJONES
HighwayUS 83
FromSH 92
ToHAMLIN NORTH CITY LIMITS
CSJ0033-03-029
Proj IDSTP 1702(131)
Work TypeCEMENT TRT BASE,1-CST,6" MILL
 
2.7524161245.3729250.000.7
Work Order06-07-17
Work Began10-12-17
Work Completed
Time Computed07-06-17
Contract Working Days242
Addl Days Granted0
Working Days Charged43
Percent Time Used17
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-03-029
BRENDA CONSTRUCTION (6.51)
CONTRACTORS SERVICE COMPANY (1.54)
DOUBLE A CONTRACTING, L.P. (1.99)
DUSTROL, INC. (1.92)
HJC FARMS, INC. (2.66)
Contract #05173221
Totals4161245.370.0029250.000.7

CountyTAYLOR
HighwayUS 83
FromNEAR FM 2404
ToNEAR S 7TH ST IN ABILENE
CSJ0033-06-107
Proj IDNH 1702(240)
Work TypePLANE,UNDERSEAL,SMA,BR RAIL,BR JTS
 
5.8518326091.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-26-17
Work Began10-16-17
Work Completed
Time Computed00-00-00
Contract Working Days294
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-06-107
A BROTHERS MILLING, LLC (1.58)
Contract #06173229
Totals8326091.950.000.000.0

CountyTAYLOR
HighwayUS 83
FromUS 83 (UNDERPASS AND TURNAROUNDS)
ToAT SOUTH 27TH (SOUTWEST DR.)
CSJ0034-01-129
Proj IDSTP 1702(246)
Work TypeREMOVE EXIST PVMNT,REPLC WITH CONC
 
0.1842346055.501691861.0572.1
Work Order07-20-17
Work Began08-14-17
Work Completed
Time Computed07-31-17
Contract Working Days87
Addl Days Granted0
Working Days Charged39
Percent Time Used44
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-129
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
HJC FARMS, INC. (1.32)
NOBLES ROAD CONSTRUCTION, INC. (15.64)
W.O.E. CONSTRUCTION (0.88)
TEX OP CONSTRUCTION, LP (4.84)
TRP CONSTRUCTION GROUP, LLC (3.03)
Contract #06173013
Totals2346055.50803585.551691861.0572.1

CountyHASKELL
HighwayUS 277
From0.436 MILE NORTH OF SH 6
To0.426 MILE SOUTH OF SH 6
CSJ0157-04-051
Proj IDNH 1702(247)
Work TypeUPGRADE SAFETY LIGHTING
 
1.839708783.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
F & W ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0157-04-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173024
Totals708783.000.000.000.0

CountyJONES
HighwayUS 180
FromNEAR ANSON WEST CITY LIMIT
ToUS 83
CSJ0296-04-019
Proj IDSTP 2017(125)
Work TypePLAN,BS RPR,ACP OV,CONC PAV INTSCTN
 
1.3732950708.422599307.73100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-29-16
Work Began01-02-17
Work Completed08-31-17
Time Computed12-29-16
Contract Working Days94
Addl Days Granted0
Working Days Charged106
Percent Time Used112
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0296-04-019
TOTAL HIGHWAY MAINTENANCE, LLC (4.46)
GONZALES CONCRETE CONTRACTORS, INC. (17.51)
Contract #10163017
Totals2950708.420.002599307.73100.0

CountyCALLAHAN
HighwayUS 283
FromAPPROX .16 MILES NORTH OF IH 20
ToAPPROX REF MARKER 308
CSJ0437-02-016
Proj IDSTP 2017(857)
Work TypeRESTORATION
 
3.3001793913.92864380.4748.1
Work Order04-12-17
Work Began05-11-17
Work Completed
Time Computed05-11-17
Contract Working Days84
Addl Days Granted8
Working Days Charged74
Percent Time Used80
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0437-02-016
ALTUS TRAFFIC MANAGEMENT LLC (0.69)
APEX HIGHWAY SERVICES LLC (0.37)
TOTAL HIGHWAY MAINTENANCE, LLC (0.97)
Contract #03173213
Totals1793913.92142070.70864380.4748.1

page 1 | page 2