I-35 NEX Central - apparent best value determination and executed agreements
I-35 Northeast Expansion Central
Apparent best value determination
Executive summary | Team List |
---|---|
Alamo NEX Construction | Alamo NEX Construction |
WBCCI, LLC | WBCCI, LLC |
Executed agreement
On July 22, 2021, TxDOT officials executed a Design-Build Contract (DBC) and associated Capital Maintenance Contract (CMC) with Alamo NEX Construction, LLC for the design, construction and capital maintenance of the I-35 NEX Central Project. This serves as notice of Final Award of the DBC and CMC for the I-35 NEX Central Project, and is hereby posted on the Project Webpage on July 28, 2021.