Notice of Availability - Mile 6 Finding of No Significant Impact
Skip to main content

Notice of Availability - Mile 6 Finding of No Significant Impact

Purpose: This notice is to advise the public that the Texas Department of Transportation (TxDOT) has issued a Finding of No Significant Impact (FONSI) for the proposed Mile 6 West Road Project from Mile 9 North to SH 107 in Hidalgo County, Texas.
   
Description: The proposed Mile 6 West Road project would consist of an urban and a rural roadway section. The urban section (from Mile 9 North to Mile 11 North) would generally consist of the following:
  • Four 12-foot-wide travel lanes (two lanes in each direction)
  • 14-foot-wide continuous center left turn lane
  • Two 10-foot-wide shoulders
  • Six-foot-wide sidewalks on each side of the roadway
  • Overall pavement width of 82 feet
  • Storm sewer system including 24-inch, 30-inch and 60-inch diameter drain pipes with multiple drainage inlets along the roadway
The rural section (from Mile 11 North to SH 107) would generally consist of the following:
  • Four 11-foot-wide travel lanes (two lanes in each direction)
  • 8-foot-wide shoulders
  • Overall pavement width varying from 60 to 76 feet
  • Portions of the rural section would accommodate a middle turning lane at intersections, which would generally be 16-feet-wide
  • Other portions of the rural section would not contain a middle turning lane
  • Storm water would be conveyed to existing outfalls via roadside ditches
The overall right of way (ROW) would be 104 feet for both the urban and rural sections. Additional ROW totaling approximately 2.3 acres would be required to provide for the enhanced safety and operational improvements of the project.

Copies of the FONSI, approved Environmental Assessment (EA) and Certification of Public Involvement are available for public inspection and reproduction at the TxDOT Pharr District Office, located at

TxDOT Pharr District Office
600 W. I-2
Pharr, TX 78577

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 16, 2014, and executed by FHWA and TxDOT.
   