Public Meeting - SH 352 North of Kearney Street to US 80 Eastbound Frontage Road
Skip to main content
Explore projects

Browse projects in your area and find opportunities to get involved.

Explore projects

Public Meeting - SH 352 North of Kearney Street to US 80 Eastbound Frontage Road

Where:

Sunnyvale Town Hall
127 Collins Road
Mesquite, TX 75182 (Map)

When:

Tuesday, Aug. 23, 2016
5 p.m. - 7 p.m.

Purpose:

The Texas Department of Transportation invites interested citizens to comment on proposed improvements to SH 352 from north of Kearney Street to US 80 eastbound frontage road in Dallas County. The meeting will be an open house format so stakeholders can come and go at their convenience.

Description:

Proposed improvements include construction of a four-lane divided urban roadway with curb and gutter, along with a raised center median. At the southern end of the project, the roadway would transition back into a four-lane urban undivided roadway to match with the existing roadway section further south. The proposed roadway section would consist of one 12-foot travel lane and one 14-foot outside shared-use lane to facilitate bicycle use in each direction. A 1-foot curb offset would be constructed on both the inside and outside lanes. The roadway would be divided by a 17-foot raised median. The typical proposed right-of-way (ROW) width is between 118 and 143 feet. Several 11-foot left and/or right turn lanes would be constructed at major intersections and median openings.

The existing signalized intersection at Clay Road would include 11-foot dual left turn lanes and a dedicated 11-foot right turn lane on the southbound direction. 5-foot sidewalk with 3-foot buffer would be constructed within the ROW on both sides of the roadway beginning from US 80 EB frontage road to just north of Old Barn Lane, followed by a 6-foot sidewalk adjacent to curb for the rest of the project limit. The total project length is approximately 1.08 miles. The proposed project would require approximately 2.7 acres of additional ROW and .2 acre of drainage easements. No residential or commercial property displacements or relocations would be required.

Written comments must be postmarked by Friday, Sept. 2, 2016, to be included in the public meeting summary.

The environmental review, consultation and other actions required by applicable federal environmental laws for this project are being, or have been, carried out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated Dec. 16, 2014, and executed by FHWA and TxDOT.