Estimate and Quantity Sheet
The estimate and quantity sheet is necessary only for state
financed contract projects and federally financed projects.
This sheet should list all bid items for the project. The
list should consist of:
- the estimated bid item quantities, showing a breakdown by control and section and the total for the entire project
- the specification item number as well as the descriptive code number and alternate number (if applicable)
- the bid item description (for example: “Installation of Highway Traffic Signals”) and the unit of measurement (for example: LS., EA, etc.).
This sheet should also show any state or city force account
items and any materials to be furnished to the contractor by the
state.