Introduction
This chapter addresses the activities that occur after the
cessation of Texas Behavioral Traffic Safety Program project and
program activity for a given fiscal year.
Project closeout activities begin when all required Performance
Reports and final Requests for Reimbursement (RFRs) have been received.
When final claims are processed, the TxDOT Financial Management
Division’s (FIN’s) procedures for preparation of the submittal of
the final federal reimbursement must be followed. Included in this
process is the final determination of what program funds were actually
expended and what the underrun amount is for carry forward to the
next program year. Part of this process also involves the final
determination of how much Section 402 funds were expended for local
benefit (40 percent minimum required) and that the state and local match
to the program met or exceeded the required minimum of 20 percent.