Amendment Process

Amendment requests are initiated by the subgrantee and submitted to the TxDOT Project Manager through the Traffic Safety Electronic Grant Management System (eGrants). If the amendment request is approved, the Project Manager will open the grant pages in eGrants to allow for changes to be made to the existing grant agreement. Once these changes have been submitted, the Project Manager reviews the changes, and if the Project Manager approves the changes, the changes are submitted to the Traffic Safety Division - Behavioral Traffic Safety Section (TRF-BTS) Program Director and the TRF-BTS Section Director for review.
If approved, a notification will be submitted to the subgrantee approving the changes. At this point, the subgrantee will obtain the signatures necessary to fully execute the new amended agreement.
To review the procedures involved in the grant amendment process, see the on the eGrants Help Page.