Project Lead Time

For projects involving mainly illumination, an appropriate lead time must be allowed for the contractor to obtain the necessary materials. Typical lead time is 90 days for conventional lighting and 120 days for high mast lighting. This gives the pole manufacturers ample time to fabricate poles.