STIP Approval
Federal regulations require the Governor or his designee to
approve the STIP. In November 2015, the Governor delegated his signature
authority on necessary transportation planning and programming related
documents to the TxDOT Executive Director. The initial Draft STIP
is adopted by the Texas Transportation Commission and certified
by the Executive Director in August and sent to FHWA/FTA for approval.
This process happens biennially in odd-numbered years (the four
years covered by the STIP would begin with an odd numbered year).
The FHWA/FTA approval letter is sent to TPP and the TxDOT Finance
Division (FIN). In addition, TPP sends the letter to all MPOs and
districts and post it online. The approval letter is also uploaded
into eSTIP portal and the approval date for the projects uploaded
into TxDOT CONNECT.
While the initial STIP requires the Commission’s approval
and adoption, revisions only require approval by the Executive Director
prior to sending forward to FHWA / FTA for federal approval.