Route Study Approval
Approval that a route study has been successfully completed
resides with both the local TxDOT District office and the TPP Division-Corridor
Planning. Approval will occur with the acceptance of study deliverables
as identified in a scope of work, whether that is prepared by TxDOT
or a consultant. If a citizen committee that has been involved with
a route study, TxDOT may request concurrence that the study has
been completed to its satisfaction.
Route study approval by the District office and TPP Division
does not commit TxDOT or the Texas Transportation Commission to
implement all recommendations noted in the final route study report.
It does not commit TxDOT and the Texas Transportation Commission
to proceed to the next phase of project development (detailed schematic
design and/or environmental impact analysis).