AFA Amendments
If there is a significant change in the scope of work, funding
or time, the district will prepare an AFA amendment that sets forth
the change and the reason for the change. Frequently this is related to
a construction contract change order, but may be necessary for non-construction
projects as well. An amendment to the AFA will frequently trigger
a change order in the related bid documents or scope of services.
Any change in the scope of the project must be consistent with TxDOT’s
change order policy and the project’s environmental document. The
contains additional information regarding project changes
and amendments.