Section 6: Project Agreements
Master Agreements
RRD
has Master Agreements with all the Class
I
railroad companies and some of the shortline railroad
companies to facilitate individual project agreements on Section
130
projects. These agreements typically cover:- Program and project documents and required approvals.
- Construction and maintenance details for preparing and approving plans, specifications, and estimates.
- Local governmentconstruction and maintenance responsibilities to for off-system public crossings.
- Cost participation.
- Authority to Order Materials and Work Orders.
- Subcontracting requirements.
- Federal-aid policy guide requirements.
- Methods of payment.
- Conditions for reimbursement.
A full agreement for an individual crossing is not required
if a Master Agreement exists.
Reimbursement Methods
There are three methods for reimbursing a railroad company.
The appropriate method depends on the scope and complexity of the
project and whether the railroad company uses its own
labor
or
a contractor to perform the work.Railroad Company Uses Own Workforce
Workforce
If the railroad company uses its own
workforce
to
perform the labor
, reimbursement is usually
made on an actual cost basis. However, if TxDOT and the railroad
company agree, reimbursement can be based on a lump sum cost estimate.
This would typically occur on smaller projects where actual cost
to the railroad company is easily estimated. Project costs and method
of reimbursement (actual or lump sum) are approved in the individual
project agreement.Railroad Company Uses a Contractor on Continuing Contract
The railroad company may use a contractor to perform the work
under a continuous agreement with the railroad company. The continuous
agreement must be for a minimum of three years. The contractor’s
costs are included in the project estimate and reimbursed at actual
cost during construction unless a lump sum arrangement is shown
in the individual project agreement. The railroad company directly
invoices TxDOT and reimburses their contractor separately.
The railroad company may also provide labor (inspection, etc.)
and include estimated costs in the individual project agreement.
Reimbursement to the railroad company will be at actual cost.
Railroad Company Uses a Contractor for Individual Project
The railroad company may choose to solicit bids for the project
from a minimum of three contractors. The lowest qualified bid will
be accepted and reimbursed at actual cost. If three bids are not received,
RRD
may
still accept the lowest qualified bidder if at least three contractors
were contacted and one or more chose not to bid the project.The railroad company directly invoices TxDOT and reimburses
their contractor separately.
The railroad company may also provide labor (inspection, etc.)
and include estimated costs in the individual project agreement.
Reimbursement to the railroad company will be at actual cost.
Individual Project Agreement
Typically, there are
four
separate paths Section
130
projects will follow after Exhibit A’s/SOW
,
cost estimates and railroad circuit
diagrams
are completed:- Exhibit B.
- Force Account Agreement.
- Construction & Maintenance Agreement.
- Crossing Closure Agreement.
Exhibit B
If a Master Agreement exists between TxDOT and the railroad
company,
RRD
prepares an Exhibit B as per terms
of the Master Agreement. The Exhibit B normally consists of:- Signed cover page providing TxDOT’s approval of work and cost estimates.
- Exhibit A (with signature from local government)or SOW.
- Cost estimates from the railroad company.
- Cost estimates from the local government (if applicable).
- Railroad companysignaldiagrams.
Depending on the terms in the Master Agreement, the Exhibit
B may need to be executed by the railroad company.
The fully executed Exhibit B is uploaded into the TRIMS Project
Management Module by the
RRD
project manager.Force Account Agreement
If a Master Agreement does not exist with the railroad company,
RRD
prepares
and negotiates a Force Account Agreement for the crossing project.
The Force Account Agreement will typically include the items listed
above shown in both the Master Agreement and Exhibit B.RRD
will coordinate any comments on the
proposed Force Account Agreement from the railroad company and revise
the agreement as needed. The agreement will be executed first by
the railroad company and then by RRD
.The fully executed Force Account Agreement is uploaded into
the TRIMS Project Management Module by the
RRD
project
manager.
Construction &
Maintenance Agreement (C&M)
Construction &
Maintenance Agreement (C&M)
If the crossing is being widened such as by installing medians,
sidewalk, or hump or vertical alignment mitigation, and if the railroad
determines the widened roadway shall require a new C&M agreement,
then the C&M Agreement process from Chapter 2, Section 4, shall
be followed.
Crossing Closure Agreement
For crossing closure projects,
RRD
will
prepare a Crossing Closure Agreement regardless of whether a Master
Agreement exists with the railroad company. The Crossing Closure
Agreement typically includes similar articles and attachments as
listed above for both a Master Agreement and Exhibit B and will
also include a copy of the signed ordinance/resolution stating the
crossing to be closed. A local government is typically given two
years from the date of the executed Crossing Closure Agreement to
invoice TxDOT for any improvements to adjacent roadways identified
in the agreement.RRD
will coordinate all comments on the
proposed Crossing Closure Agreement from participating parties (district,
railroad company or local government) and revise the agreement as
needed prior to submitting to all signing parties for execution.
For three-party agreements, the agreement is usually executed first
by the railroad company, then the by the local government, and finally,
by RRD
. For two-party agreements, the agreement
will be executed first by the railroad company and then by RRD
.The fully executed Crossing Closure Agreement is uploaded
into the TRIMS Project Management Module by the
RRD
project
manager.After Project Agreement is Executed
RRD
distributes a copy of the executed
Exhibit B, Force Account Agreement or Crossing Closure Agreement
to:- The District.
- The railroad company.
- The local government.
Exhibit L
At the conclusion of each program year,
RRD
will
track the final list of crossing locations selected for improvements
with Section 130 funding. This list will consist of the preliminary
project list, with any No Further Action projects removed, and any
additional projects added. The list is referred to as the Exhibit
L.
Advanced Funding Agreements
Advanced Funding Agreements
Advanced Funding Agreements (AFA) are coordinated between
the local government and the affected district. Once executed, RRD
will obligate any funds needed per the terms of the AFA. An AFA
is typically executed to cover design and/or construction by local
agencies for civil work funded by Section 130. Any railroad work
on the project is typically handled by a TxDOT Section 130 agreement
between TxDOT and the railroad company and shall be referenced,
but the amount not part of the local government AFA.
For off system work covered by SOW only, a no cost or similar
AFA shall be executed between TxDOT and the local government prior
to federal obligation.