Initial Programming
RRD
will compile estimated preliminary
engineering costs for Section 130
projects
and request a separate Control Section Job (CSJ) project
number
from the Finance Division Letting Management Section
for system-wide preliminary engineering for:- UPRR.
- BNSF.
- CPKC.
- Shortline railroad companies (all under the same CSJ).
The Finance Division Letting Management Section will compile
a Federal Project Authorization & Agreement (FPAA) to be sent
to the Federal Highway Administration (FHWA) for each of these CSJs.
The FHWA will review and approve the FPAAs to obligate federal funds
for preliminary engineering. This occurs prior to issuing a System-wide
PE Agreement to the railroad companies.