Section 5: Project Agreements
Master Agreements
TxDOT has Master Agreements with all the
Class I
railroad
companies and some of the shortline railroad companies to facilitate
individual project agreements for work on replanking program projects.
These agreements typically cover:- Process for adding and deleting crossings for the program each year.
- Program and project documents and required approvals.
- Construction and maintenance responsibilities of TxDOT and the railroad company.
- If TxDOT will pay railroad company on an actual cost basis or fixed cost per track foot of replanking (sometimescategorizedby daytime or night/weekend installation rates).
- Process of approving cost per track foot each program year.
- Work Orders.
- Inspection of materials.
- Conditions for reimbursement.
Reimbursement Methods
There are three methods for reimbursing a railroad company.
The appropriate method depends on whether the railroad company uses
its own
workforce
or a contractor to perform
the work.Railroad Company Uses Own Workforce
Workforce
If the railroad company uses its own
workforce
to
perform the work, reimbursement is usually made on a lump sum basis.
The reimbursement for an individual crossing will be determined
by multiplying the length of crossing surface panels along the track
by the cost per track foot agreed upon with the railroad company.
Lump sum reimbursements typically occur when a Master Agreement
exists with the railroad company.Actual cost reimbursement to the railroad company may also
be used. In these scenarios, a cost estimate is developed prior
to construction by the railroad company and approved by
RRD
.
Actual cost reimbursement is typically used when a Master Agreement
does not exist with the railroad company.Project costs and method of reimbursement (actual or lump
sum) are approved in the individual project agreement.
Railroad Company Uses a Contractor on Continuing Contract
The railroad company may use a contractor to perform the work
under a continuous agreement with the railroad company. The continuous
agreement must be for a minimum of three years. A copy of this agreement
must be provided to
RRD
.The contractor’s costs are included in the project estimate
and reimbursed at actual cost during construction unless a lump
sum arrangement with the railroad company is shown in the individual project
agreement. The railroad company directly invoices TxDOT and reimburses
their contractor separately.
The railroad company may also provide labor (inspection, etc.)
and include estimated costs in the individual project agreement.
Reimbursement to the railroad company will be at actual cost.
Railroad Company Uses a Contractor for Individual Project
The railroad company may choose to solicit bids for the project
from a minimum of three contractors. The lowest qualified bid will
be accepted and reimbursed at actual cost not to exceed the original
bid. A Form 1891 (Detailed Estimate for Railroad Solicitation of
Bids) is
completed
for each bidding contractor
which groups
various costs on the project and
helps to ensure balanced bids. If three bids are not received, RRD
may
still accept the lowest qualified bidder if at least three contractors
were contacted and one or more chose not to bid the project.The railroad company directly invoices TxDOT and reimburses
their contractor separately.
The railroad company may also provide labor (inspection, etc.)
and include estimated costs in the individual project agreement.
Reimbursement to the railroad company will be at actual cost.
Refer
to RRD Crossroads website for more information.
Individual Project Agreement
Typically, there are two separate paths replanking program
projects will follow after Exhibit A
/SOW
and
cost estimates have been completed and approved:- Project Notice.
- Force Account Agreement.
Project Notice
If a Master Agreement exists with the railroad company,
RRD
will
prepare a Project Notice. The Project Notice normally consists of:- Signed cover page providing TxDOT’s approval of work, cost estimates and selection of contractor (if railroad company solicited bids from contractors).
- Exhibit A/SOW.
- Cost estimates from railroad company or railroad company’s continuing contractor (if applicable).
- Cost estimates from bidding contractors (if applicable).
- Standard TCP if SOW is used.
Depending on the terms in the Master Agreement, the Project
Notice may need to be executed by the railroad company.
Force Account Agreement
If a Master Agreement does not exist with the railroad company,
RRD
prepares
and negotiates a Force Account Agreement for the crossing project.
The Force Account Agreement will typically include the items listed
above shown in both the Master Agreement and Project Notice.RRD
will issue the Force Account Agreement
to the railroad company for comments. Once comments are resolved,
the railroad company will execute the agreement and return to RRD
for
final execution.After Project Agreement is Executed
RRD
distributes a copy of the executed
Project Notice or Force Account Agreement to: - District.
- Railroad company.
The fully executed Project Notice or Force Account Agreement
is uploaded into the TRIMS project management module by
RRD
.RRD will coordinate with FIN to setup the CRX project
in Peoplesoft.