Project Agreement Process
After all comments are resolved, the
RRD
contract
specialist will draft an appropriate agreement giving permission
for the work to be performed:- CrossingPermit Agreement: Used for a new track crossing a highway on TxDOT right of way.
- Joint Use Agreement: Typically used for double tracking projects, maintenance projects or other railroad capital improvement projects on railroad right of way which impact a highway.This may include the railroad adding a track parallel to a state road, and a slope or other permanent use of state right of way is needed.
- Letter Agreement: May be used for minor work with minimal impact to highway facilities or TxDOT right of way.
These agreements usually specify the railroad company will
be responsible for all costs involved in the construction of the
project and will not include any attachments other than an Exhibit
A plan set. A cost estimate for work performed by TxDOT would not
be included since this would be covered by a Donation Agreement.
Typical timelines for execution of these agreements are six
to nine months from initial submittal of Exhibit A plan set to full
agreement execution.
Project agreements are uploaded into the TRIMS project management
module by
RRD
.If driveway access is needed or driveway locations need to
be modified, approval from the
TxDOT area office
via
a driveway permit is required
. Districts will
issue any required roadway closure agreements.