Donation Agreements
One key difference between TxDOT construction projects and
railroad capital improvement projects is TxDOT cannot extend credit
to another party for services provided prior to reimbursement. Therefore,
a Donation Agreement is needed between TxDOT and the railroad company
so the railroad company can provide funding for the work prior to
the work being performed. TxDOT employees may charge time and materials
to the project. Once the project is complete, any funding paid via
the Donation Agreement above what was charged by TxDOT is reimbursed
to the railroad company.
Once a district is notified of an impending railroad capital
improvement project, a decision must be made by the district on
whether a Donation Agreement should be pursued between TxDOT and
the railroad company. Donation Agreements allow TxDOT to be reimbursed
for labor and materials provided on railroad capital improvement
projects. Some examples of TxDOT services may include:
- Reviewing railroad company plans and support documentation.
- Attending project meetings and diagnostic inspections.
- Drafting permit agreements.
- Coordinating utility locates and relocates.
- Providingtraffic control (if TxDOT agrees).
- Reviewing traffic control plans.
- Reimbursement for salvage value of active warning devices paid for by public funds being removed by the railroad company.
- Project inspection.
- Public outreach efforts.
- Other labor and materials TxDOT may provide during construction.
A Donation Agreement typically includes an attached estimate
of TxDOT services as well as a project location map. The agreement
will specify design standards required from the railroad company,
requirements on utility adjustments, and insurance requirements
for railroad companies working on TxDOT right of way.
Donation Agreements usually take three to six months to execute.
If the district decides to pursue a Donation Agreement, any plans
developed by the railroad company cannot be reviewed until the agreement
has been fully executed. In some cases, the district may decide
not to pursue a Donation Agreement. Reasons may include:
- Scope of work by TxDOT is minor (plan review only).
- No lane closures are involved.
- Project provides benefit to TxDOT,
- Project affectsanotherTxDOT project schedule.
- TxDOT agrees to forego Donation Agreement based on negotiations with railroad company.
If a Donation Agreement is executed, it will be recognized
by the commission typically within one month of the agreement being
executed.