Proposed At-Grade Crossings
Upon receiving a request for a crossing
across state
right of way
, the district first investigates the possibility
of the applicant (railroad company or private industry or both)
obtaining rail service by alternate means that will not require
an additional highway crossing. This usually means servicing through
a different railroad company or through joint use of a nearby existing permitted
track
crossing or rail line. If an alternate plan is impracticable
,
the district should forward the permitted
track
request to RRD
, along with a report and recommendations. The
report should include: - A map showing the location of the proposedpermittedtrack crossing.
- AADT at this location.
- Applicant’s estimate of the number and length of trains anticipated to cross the highway during each 24-hour period.