TxDOT Review
RRD
is mailed a copy of an NOI by the
local government or city. RRD
forwards the
NOI to the district railroad coordinator for any comments and compiles
these comments with any comments from RRD
for
response to the local government.NOIs are reviewed to ensure the proposed Quiet Zone:
- Meets requirements described in this chapter.
- Meets requirements typically included on FSP projects.
- Is calculated correctly if the Quiet Zone applies because the QZRI is less than or equal to the RIWH or NSRT.
- Individual crossing data (traffic counts, train counts, etc.) is correct if the Quiet Zone applies because the QZRI is less than or equal to the RIWH or NSRT.
- Includes all crossings along the section of rail indicated as shown in TRIMS.
For more information on reviewing plan sets, see Chapter 7.
Any data discrepancies noted between the NOI and TRIMS are
verified between
RRD
, the local government
and the railroad company. RRD
coordinates any
inventory updates in TRIMS and with the FRA.