Chapter 10: Other Rail-Highway Programs
Section 1: Railroad Signal Maintenance Payment Program
Overview
The Railroad Signal Maintenance Payment Program is managed
under Category 10 (Supplemental Transportation Projects) of the
UTP as a bank balance allocation program to provide a fixed annual unit
payment to railroad companies for maintenance of railroad signals.
Each year, the Texas Transportation Commission authorizes the total
amount of funding for the program.
Only open, public, in service, active at-grade crossings on
the state highway system are eligible for the program, excluding
any industry spur track crossings located on the state highway system
covered by a rail spur permit. It is funded with 100% state funds.
Funding for the program is typically around $1.1 million annually,
and payment is provided per crossing on the following schedule:
- Mast flashers: $289.
- Cantilevers: $385.
- Gates: $770.
Payment for a crossing is made based on the highest level
of protection present at the crossing. For example, if a crossing
includes both gates and cantilevers on both approaches, $770 would
be paid for the entire crossing.
Schedule of payment is subject to change on an annual basis.
Verification of Warning Devices
Before payment to the railroad company can be made under the
Railroad Signal Maintenance Payment Program, the type of warning
devices in place must be verified.
RRD
runs
an inventory report annually via the TRIMS database and sends a
letter with the following information to each railroad company:- Listing of all public on-system at-grade crossings listed as active or passive.
- Type of warning devices at each of the active crossings.
A warning device must be in place at the beginning of TxDOT’s
fiscal year to be eligible for payment for that fiscal year. TxDOT’s
fiscal year begins September 1
of the previous calendar
year through August 31 of the fiscal year
.For example, if a mast flasher was upgraded to a gate on September
15, 2015, payment for a gate would not occur until fiscal year 2017.
For fiscal year 2016, payment would be paid for a mast flasher.
Any discrepancies are coordinated by
RRD
with
the railroad company and the district railroad coordinator. If necessary, RRD
will
update inventory data in TRIMS.The railroad company must sign and return the letter verifying
inventory prior to TxDOT issuing payment.
Payment of Rail Safety Inspection Fee
TxDOT rail safety investigators conduct safety inspections
of railroad facilities and equipment. Each year, railroad companies
are required to pay a fee to TxDOT, authorized under 43 TAC §7.41, in
support of this program.
TxDOT will not pay a railroad company under the Railroad Signal
Maintenance Payment Program until the railroad company is current
in payment of TxDOT rail safety program fees.
Programming
RRD
will request a single CSJ each program
year from the Finance Division Letting Management Section based
on funding for the program in that year.Payment to Railroad Companies
After concurrence is reached on the inventory list between
TxDOT and the railroad company and the railroad company has paid
any rail safety inspection fees,
RRD issues a memo to
FIN to pay the railroad company
. Payment is made prior
to the end of the TxDOT fiscal year.