Maintenance Notice
Letter Execution
Maintenance Notice
Letter Execution
The railroad company will review the submitted Maintenance
Notice Letter or Maintenance Consent Request further. This review
could take up to six months.
As of 2021, the Union Pacific Railroad requires a Maintenance
Consent Letter with Contractor Endorsement (MCL) on all maintenance
projects in their right of way. The received MCL will clear a project
for letting and takes the place of traditional contractor right
of entry. The MCL will then be distributed by RRD to all necessary
parties for execution by the contractor.