Guidelines on Projects with Traffic Signal Preemption
- Correct timing is identified on plan sheet (equipment response time, advance preemption time, clearance time, minimum time, and buffer time). Any traffic signal timings shown match timings in preemption form (TxDOT Form 2304).
- All signal heads shown.
- Phasing diagram for normal operation shown.
- Preemption phasing diagram shown with right of way transfer, track clearance, dwell or limited cycle, and exit phases.
- Plans identify conduits and traffic signal cable between traffic signal cabinet and rail cabin, includingresponsible party for providing and installingmaterials.
- Traffic signal cable should be a minimum12conductor cable.
- Plans clarifyresponsible party for traffic signal maintenance and operation.
- Protected left turn provided for traffic on track clearance phase (if conflicting traffic is approaching the traffic signal from opposite side of the intersection).
- Battery back-up provided forTSC.
- Traffic signal poles do not block active warning devices.