Guidelines on Construction Project Exhibit A’s
- Title sheet project description reflects work in railroad right of way, not the overall PS&E.
- Project plan view layout included if work impacts multiple rail lines or crossings.
- Fencing parallel to track to discourage trespassing shown (ifrailroad required).
- Impacts to any existing railroad signals shown.
- Ensure Railroad Requirements Sheets are included at end of Exhibit A and are thecurrentversion. Use Bridge or Non-Bridge sheets depending on project scope. Only sheet 1 of 3 may be modified; sheet 1 must be sealed, signed, and dated by the licensed Texas Professional Engineer.
- Any absolute track windows requested from the railroad company shown. (If so, this needs to be requested from the railroad company. Typically applies to overpasses over rail yards or underpasses.)
- Any required right of way acquisitions shown.
- Direction of increasing railroad milepost shown.