New At-Grade Crossings
Most railroad companies strongly oppose public projects that
introduce new at-grade crossings. New at-grade crossings add maintenance
and liability costs to a railroad company. However, in some cases,
new at-grade crossings are unavoidable and railroad companies are
willing to allow them if two to three other existing public at-grade
crossings are closed and anticipated traffic counts at the new crossing
do not exceed the combined traffic counts of the closed crossings.
The TxDOT
RRD Rail Letting Section
serves as
the office of primary negotiation with the railroad companies in
these scenarios.