Accessing Railroad Right of Way
The project designer should become familiar with the project
site and determine how project work within railroad right of way
will be constructed. Temporary at-grade crossings are discouraged
and may add both project cost and risk. Whenever possible, designers
should aim to design any temporary pavement, ramps
or
detours
that assist a contractor in construction
of
the project to eliminate the need for a temporary
at-grade crossing.If a temporary at-grade crossing is needed, it should be included
in the Exhibit A for the railroad company to review up front and
will be included in the C&M Agreement.