TRIMS Project Management Module
The project management module in TRIMS includes information
for all types of rail-highway projects. Some data in the project
module includes:
- CSJ and project numbers.
- Project type (construction, replanking or safety).
- DOT numbers impacted.
- Locationinformation(city, county, roadway, and district).
- Letting dates.
- Listing of project steps and completion dates.
- Project attachments including diagnostic notes, preemption forms, PE Agreements, C&M Agreements, Authority to Order Materials, Work Orders, inspection notes, approved invoices, Completion Letters, Completion Checklists, etc.
- Description of project and scope of work.
- Journal entries.
- Basic cost information.
RRD
and district railroad coordinators
share responsibility for project updates in TRIMS. RRD
creates
the projects, adds basic project information
and
steps, and typically uploads any agreement information and Completion
Checklists to the project. Work Orders, inspection diaries, approved
invoices, and Completion Letters are uploaded by districts.Only TxDOT users have access to the TRIMS project management
module.
Consultants working on RRD projects may be allowed
access to TRIMS on a case-by-case basis.