5% Cost Reimbursement
On projects including a 5% cost participation from the railroad,
the district railroad coordinator will notify
the RRD
contract specialist
in writing when traffic has been
shifted onto the new roadway and the at-grade crossing has been
removed. RRD
will issue a letter to the railroad company
requesting that the 5% cost participation amount shown in the C&M
Agreement be paid to TxDOT.FIN will confirm with
RRD
and the district
when payment has been received. Receipt of payment from FIN is uploaded
into TRIMS by RRD
.