5% Cost Reimbursement

On projects including a 5% cost participation from the railroad, the district railroad coordinator will notify
the RRD contract specialist
in writing when traffic has been shifted onto the new roadway and the at-grade crossing has been removed.
RRD
will issue a letter to the railroad company requesting that the 5% cost participation amount shown in the C&M Agreement be paid to TxDOT.
FIN will confirm with
RRD
and the district when payment has been received. Receipt of payment from FIN is uploaded into TRIMS by
RRD
.