Final Inspection

The district railroad coordinator should schedule a final inspection of the project as soon as practical with the railroad company after construction is complete and any active railroad warning devices have been placed in service. At request of the district,
RRD
may arrange the final inspection
of non-construction and maintenance projects
.
Final inspection includes plan verification and inspection of:
  • All work performed by the road authority or contractor.
  • All work performed by railroad company or contractor.
  • Utility adjustments.
  • Sight distance on approaches to at-grade crossings.
For sample inspection reports for
Section 130
and replanking projects, see the
RRD Crossroads website
.
Any findings in the final inspection will be noted in a final inspection report to the railroad company which must be resolved prior to submitting a final invoice.