Authority
    TxDOT District Engineer, or designee, has approval authority for Utility Agreement Assemblies, Supplemental Utility Agreements, and Emergency Work Authorizations.
The following items are required for a District to initiate local approval of a Utility Agreement Assembly. The District must:
- obtain ROW Division Project Release;
 - create a Utility ID;
 - environmental clearance;
 - approve utility consultant engineering contract, if applicable;
 - verify corporate succession and granting of signature authority with ROW Division;
 - confirm that utility accounting systems are acceptable to TxDOT for audit and payment purposes;
 - have updated AP 152 on file;