General
When a non‑interstate right of way project is converted to Federal-aid participation, the following requirements apply:
- Limit TxDOT and Federal participation to the adjustment of facilities located on utility-owned compensable interests.
- Use form .
- Follow the State Procedures requirements in of this chapter, which outlines the required data that must be submitted to ROW Division and to FHWA to receive approval of utility agreements under State Procedure . This information is required on each right of way project.
- When adjustments involve facilities located on both highway right of way and utility-owned right of way, determine an eligibility percentage according to .