Procedures for Computing Elective Betterment Credit
- Prepare a plan and estimate of cost for replacement of the existing facility in the most economical manner, as required by the transportation construction project:(A).
- Prepare a second plan and estimate including the betterments that the utility elects to build:(B).
- Subtract the two (above items) from one another to arrive at the difference between the two:(B) minus (A) = (X)
- Compute a betterment credit percentage based upon the ratio of the result(X)in the bullet above to the betterment estimate(B):
= Elective Betterment Credit Percentage
- Apply the elective betterment percentage to the final billing of actual costs incurred in building the “bettered” facilityBEFOREdeducting accrued depreciation, if applicable, and salvage credits.
Estimated Total Cost of Relocation: | $1,000,000 (B) |
Non-betterment Estimate | ‑ 700,000 (A) |
Elective Betterment Credit | $ 300,000 (difference) (X) |
(X) / (B) = % (Percentage) | 30% Betterment Credit |
Total Billing (including betterments) | $1,200,000 |
Less 30% Betterment Credit | $ 360,000 |
Less: Accrued Depreciation (if applicable) | $ -0- |
Less: Salvage (if applicable) | $ 122,000 |
Eligibility Ratio (if applicable) | $ -0- |
Estimated Reimbursement | $ 718,000 |
*Actual cost may differ from the estimated cost.
Care should be taken when arriving at the estimated cost of relocation to avoid having to bid.
- Reimbursable Miscellaneous Items:
- Storm Water Pollution Prevention Plan (SWPPP): The general requirements established by the EPA maintain that the contractor must have a National Pollution Discharge Elimination System (NPDES) permit for certain construction activities.
- Security: The utility may contract with a security service to provide security for their on-site equipment and materials during the utility adjustment.
- Revegetation: In accordance with the UAR, the utility is responsible for reseeding and re-sodding to reduce erosion when the utility installation is complete. It is also required to reshape, reseed, or re-sod the area when, within six months after utility installation, settlement or erosion occurs.
- Product Loss (not to be confused with revenue loss): The following 4-step calculation will be used to estimate gas loss when relocating pipelines containing natural gas:
- (1) FPV = 1 + P2 / 1000 * 0.847(2) V2 = [P1 * [D1 / 12 * D1 / 12/4] * L1 * [[P2 + 14.65] / 14.65] * FPV] / 1000(3) R1 = V2 * 1000 * S1(4) Gas Loss = R1 / 2000.Where:FPV = Super-compressibility factorP2 = Pressure (PSIG)V2 = Volume of gas in pipeline segment (in MCF)P1 = Original absolute pressureD1 = Internal diameter of pipeL1 = Length of pipelineR1 = Gas release weight in lbs/cfS1 = Sample of gas in lbs/cf.
- Trench Safety Plan
- Testing and Removal of Contaminated Soils