SUE and Utility Coordination Contracts

The utility coordinator will need to understand the District’s process on the procurement of a SUE contract through the PEPS Division. Each District has a consultant contract engineer or Manager to assist you in setting up a SUE contract.
The district may request a contractor solely for SUE, utility coordination services, or a combination of the two from PEPS Division.
The SUE and utility coordination contract may include the following activities:
  • SUE;
  • Coordination meetings;
  • Utility conflict determination;
  • Utility conflict resolution;
  • Preparation of utility agreement assemblies;
  • Review of PS&E;
  • Monitoring of progress, including inspections; and/or
  • Preparation of Joint Use Agreements and verification of “As-Built” plans.
A SUE contract may be funded through:
  • Design Division,
  • ROW Division, or
  • District local contract.
  • LPA