Right of Way Release - Right of Way Sub-process Activity IV
- Participants
- TxDOT Right of Way Representative
- TxDOT ROW Division
- TxDOT Finance Division
- Objectives
- Authorize right of way acquisition and utility adjustment activities.
- Notice to TxDOT Finance Division for right of way funds authorization.
- Activity Narrative
- The Right of Way Release is the authorization by the TxDOT ROW Program Office for the District to begin right of way project activities. The Right of Way Release is a prerequisite to subsequent Right of Way Sub-process activities required to authorize reimbursable utility adjustments. It also acts as a notice to the TxDOT Finance Division to issue fund authorization. The request for Right of Way Release will be initiated by District Right of Way and must be accompanied by a statement that the District is prepared to start the work. The release is conditioned upon completion of the following requirements:
- right of way map approval
- Relocation plan
- Rodent control documentation
- Right of way project cost estimate
- Environmental release
- Executed contractual agreement, with funding if applicable.