Perform Utility Adjustment - Right of Way Sub-process Activity XI
- Participants
- Utility Construction Representative
- Utility Construction Inspector
- TxDOT Construction Contractor
- TxDOT Project Construction Engineer
- TxDOT Utility Liaison
- Objectives
- Accomplish the adjustment to utility facilities in an efficient and timely manner.
- Coordinate the adjustment of utility facilities with the development, scheduling and performance of the TxDOT construction contract.
- Activity Narrative
- With particular emphasis placed on the proper documentation of material, labor, and equipment incorporated in the work, it is important that both TxDOT and the utility provide for proper inspection. This will also ensure compliance with the UAR. The TxDOT Utility Liaison will be responsible for assuring that adequate communication and coordination occurs between the appropriate participants to accomplish the adjustment and documentation in a competent manner.