Federal Project Authorization and Agreement (FPAA)- Right of Way Sub-process Activity III (a)

  • Participants
  1. TxDOT Right of Way Representative
  2. TxDOT Division
  3. Federal Highway Administration (FHWA)
  • Objectives
  1. Secure right of way project release on Federal-aid right of way projects.
  2. Approval of federal cost participation.
  • Activity Narrative
  1. The Federal Project Authorization and Agreement (FPAA) documents the approval for Federal cost participation in a right of way project. It must be obtained as a prerequisite for the TxDOT ROW Program Office.
  2. Necessary information for the FPAA will include the utility name(s), locations of existing facilities by station number and estimated cost of adjustment(s) by utility.
  3. The FPAA may be requested concurrently with the Alternate Procedure Approval (Sub-process Activity V).