Exchange of Project Specific Information: Initial Project Notification - Process Activity II

  • Participants
  1. Responsible Party
    • TxDOT Project Design Engineer
  2. Necessary Parties
    • Local Agency Representative
    • Utility Liaison
    • TxDOT Design Consultant
    • TxDOT Right of Way Representative
    • TxDOT Utility Liaison
  3. Interested Parties
    • TxDOT Design Team
    • TxDOT Environmental Representative
    • TxDOT Advance Planning Engineer
    • Other TxDOT Parties as Applicable
  • Objectives
  1. Provide preliminary project description, scope, and letting schedule to utilities.
  2. Set date for preliminary design meeting.
  3. Identify TxDOT Project Design Engineer & TxDOT Design Consultant if appropriate.
  4. Request identities of utility contacts to be assigned to the TxDOT project.
  5. Request block maps/mark ups from utilities.
  • Activity Narrative
    Prerequisites to the Initial Project Notification include completion of a preliminary schematic or other general representation of the proposed project layout. The TxDOT Project Design Engineer has been appointed and, if applicable, a TxDOT Design Consultant has been retained. A list of potentially impacted utilities is compiled, right of way mapping has begun, and TxDOT is ready to begin design of the facility. This activity in “The Process” will typically take the form of a project specific letter of information prepared for distribution to all known utilities and other concerned parties. The purpose of the Initial Project Notification is to advise utilities of the general characteristics of an upcoming TxDOT project and to provide an illustration of the project footprint for mark-up of utility facility locations, which occupy the project area. The notification will also introduce the Responsible Party and other TxDOT contacts for the project and request the submittal of utility block maps, as-built plans or system drawings to indicate utility facility locations and other features. The Initial Project Notification will announce the time and location of the Preliminary Design Meeting (Process Activity III) below and should be sent out no less than two weeks before to ensure full attendance and to allow adequate time for compiling requested information by the utilities.