Division Responsibilities
    - Create an electronic utility list of all “U” numbers / Utility IDs for the project acquired by computerized application.
 - Retrieve files from the utility list.
 - Retrieve any additional files discovered in a physical search of the ROW Division Utility Portfolio Section files.
 - Examine all files for final payment and discard duplicates.
 - Review all Utility Joint Use Agreements, recorded quitclaims, release of easements, and subordination of mineral leases.Retain all keep items for permanent records in OnBase, the electronic content management system.
 - Reduce approved plans or “as-built” plans to half scale.Retain for permanent records in OnBase the electronic content management system.
 - Make annotations on the title sheet of the right of way map listing “U” numbers / Utility IDs applicable to the project.
 - Deliver files to Contracts and Finance Section with the completed Utility Branch closeout notice.
 - During ROW Program Office review of the District’s project financial and records closeout request, if any items in the file are missing or incorrect, the Division will:
- notify the District of its findings and request action to resolve any items noted;
 - notify its Contracts and Finance Section that project closeout will be delayed due to the items noted; and
 - check with the District on a quarterly basis until outstanding items are resolved.