Supporting Documentation Required for Partial Payment Requests
All Partial Payment Requests must be prepared in a format that corresponds with the Estimate Section of the approved Utility Agreement. Each item must be listed according to its corresponding item in the estimate. Partial payments will not be made until all items on the cost estimate related to Buy America or State Iron and Steel Preference Provisions have been submitted and verified for compliance.
Materials | |||
---|---|---|---|
Type | Unit | Unit Cost | Invoice Amount |
8" PVC Pipe | 85 ft | $2.00/ft | $170.00 |
Labor | |||
---|---|---|---|
Type | Unit | Unit Cost | Invoice Amount |
Draftsperson | 20 hrs | $40/hr | $800.00 |
Variations from the standard format will require TxDOT approval.
All payment requests must be supported with adequate documentation to support the reimbursement of actual costs. Below are preferred and the acceptable examples of supporting documentation. Documentation requiring certification should be certified by appropriate utility personnel as being true and correct. The first page of Certified Time Sheets and Certified Utility Company accounting ledger should be on company letterhead with the company logo, a statement of accountability, and a signature of an officer of the company or representative with signature authority.
Cost Type | Preferred Documentation | Acceptable Documentation |
---|---|---|
Utility Labor | Certified Time Sheets | Certified Utility Company's accounting ledger |
Utility's Equipment | Certified Time Sheets | Certified Utility Company's accounting ledger |
Materials and Supplies | Invoice from Supplier | Inspector's diary of material on hand or installed and the Certified Utility Company's accounting ledger |
Consultant Engineering | Invoice from Consultant | Completed Plan Sets and Certified Utility Company's accounting ledger |
Contractor Services | Invoice from Contractor | Inspector's diary or approval of work and the Certified Utility Company's accounting ledger |