Billing Assembly Package
    Prior to processing payment, form 
 should be attached.
Final Billings
      - Electronic submittal (one PDF document)
- show beginning and ending dates of adjustment on billing or attachment
 - statement reflecting address of records/accounts for audit and mailing purposes (TINS)
 - invoices
 - salvage inspection statement
 - bid specifications and bid tabulation
 - district’s transmittal memo, with clarification, recommendation, and an explanation of any unusual underruns or overruns
 - transmittal memo from District to Division must be signed by District Engineer or designee
 
 - Attachments
- Electronically submit one recorded original of form or or whichever is applicable, if not previously submitted.
 
 - Special Considerations
- Any conditions applied at agreement approval should not be reflected in billing.
 - Format of billing must agree with format of estimate, so correlation is possible.
 - Billings must be compared and reconciled to the approved agreement, plans, and estimate.
 - Deduct any betterment not originally included in the agreement. Otherwise, betterment ratios must be the same as originally approved.
 - Consulting engineering services in the billing must have prior District approval, with an approved contract in District files.
 - Major changes in the scope of work, exceeding +/- $100,000.00 or +/- 25% of the approved agreement, must be approved in an amendment (Supplemental) to the agreement by the District or ROW Division.
 - Minor changes must be explained in transmittal memo sent to the ROW Program Office.
 - Identify low bid contractor used.
 - Attach a copy of the appropriate pages of the inspector’s project diary in District files and use it to verify charges on the billing.
 - Correctly apply the approved betterment credit, accrued depreciation, salvage credit, and eligibility ratio.
 - Show the beginning and ending work dates.
 - Check that all extensions and totals are correct.