Billing Assembly Package

Prior to processing payment, form should be attached.
Final Billings
  • Electronic submittal (one PDF document)
    • show beginning and ending dates of adjustment on billing or attachment
    • statement reflecting address of records/accounts for audit and mailing purposes (TINS)
    • invoices
    • salvage inspection statement
    • bid specifications and bid tabulation
    • district’s transmittal memo, with clarification, recommendation, and an explanation of any unusual underruns or overruns
    • transmittal memo from District to Division must be signed by District Engineer or designee
  • Attachments
  • Special Considerations
    • Any conditions applied at agreement approval should not be reflected in billing.
    • Format of billing must agree with format of estimate, so correlation is possible.
    • Billings must be compared and reconciled to the approved agreement, plans, and estimate.
    • Deduct any betterment not originally included in the agreement. Otherwise, betterment ratios must be the same as originally approved.
    • Consulting engineering services in the billing must have prior District approval, with an approved contract in District files.
    • Major changes in the scope of work, exceeding +/- $100,000.00 or +/- 25% of the approved agreement, must be approved in an amendment (Supplemental) to the agreement by the District or ROW Division.
    • Minor changes must be explained in transmittal memo sent to the ROW Program Office.
    • Identify low bid contractor used.
    • Attach a copy of the appropriate pages of the inspector’s project diary in District files and use it to verify charges on the billing.
    • Correctly apply the approved betterment credit, accrued depreciation, salvage credit, and eligibility ratio.
    • Show the beginning and ending work dates.
    • Check that all extensions and totals are correct.