Right of Way Releases for Utility Work

For related information, see of the
ROW Acquisition Manual
.
  • Utility Only Project Release. This release is typical of projects where no right of way acquisition has been planned, but reimbursable utilities are encountered. Generally, no other right of way work is performed under the ROW CSJ/ROW Project ID assigned to the project. Costs may be charged against the ROW CSJ/ROW Project ID when this type of release is used. The requirements for this type of release are:
    • Commission Minute Order - Project Authorization
    • Environmental clearance
    • Request from the District for release
    • Federal Project Authorization and Agreement (FPAA), if applicable, for Federal funding
    • Contractual Agreement with LPAs , if applicable; include three copies of the agreement
    • Copy of the check for the LPA's contribution amount
    • Copy of the LPA's resolution
  • Full Authority Release. All costs may be charged to the ROW CSJ/ROW Project ID. When issued by the ROW Program Office, the Full Authority Release includes utility work and all other right of way activities. This would include processing of the Utility Agreement Assembly, acquiring replacement utility right of way, physical adjustment of utility facilities, and reimbursement of eligible cost incurred. Issuance of a full right of way release is contingent upon completion of the following:
    • Approved schematic
    • Approved right of way map submitted to the ROW Program Office
    • Right of way project cost estimate
    • Environmental clearance
    • Federal Project Authorization and Agreement (FPAA), if required
    • Executed contractual agreement with LPA, including funding, if applicable.