General Accounting Office Report
The Transportation Equity Act for the 21st Century (TEA-21) directed the United States General Accounting Office (GAO) to assess the impact that delays in relocating utilities were having on the delivery and cost of Federal-aid highway and bridge projects. The reader may review the entire
for more information.
In summary, the report identified the following areas that may cause delays:
- Short periods for the State to plan and design a project.
- Relocations given low priority by utilities.
- Increased workload on utility adjustment crews because of an increase in highway and bridge construction.
- Delays in starting utility adjustment because some utilities would not start work until a construction contract was advertised or let.
- The phasing of construction and utility relocation work was out of sequence.
- There was inadequate coordination or sequencing among the utilities.
- Inaccurate locating and marking of existing utility facilities.
- Delays in obtaining right of way.
- Shortages of labor and equipment for the utility contractor.
- Project design changes that require changes to utility relocation designs.
- Utilities were slow in responding to contractor’s requests to locate and mark underground utilities.