Description of Procedures
District Engineer or designated representative is responsible for comprehensive coordination of the utility accommodation process.
Use the personnel listed above for technical expertise and consultation throughout project development.
The responsibility for the administration of property rights issues, utility policy, and reimbursement of eligible utility adjustments remains with Right of Way personnel.
Consider utility representatives for attendance at each Feasibility Scoping Meeting, Preliminary Design Conference, and Design Conference.
The “TxDOT-Utility Cooperative Management Process” was developed to consider utility concerns as a TxDOT project advances through the planning, design, acquisition, and construction phases of development. “The Process” includes the following activities:
- Annual Meeting(s)
- Initial Project Notification
- Preliminary Design Meeting(s)
- Field Verification
- Design Conference
- Intermediate Design Meeting(s)
- Final Design & Initial Construction Coordination Meeting
- Pre-letting Utility Meeting
- Utility Meeting After Award
- Utility Coordination Meeting During Project Construction.
The “Right of Way-Utility Adjustment
” was developed to provide detailed information specific to property rights and reimbursement requirements. The Subprocess includes the following activities:
- Early Right of Way Release for Utility Adjustments
- Field Verification
- TxDOT-LPA Right of Way Contracts
- Federal Project Authorization and Agreement
- Right of Way Release
- Alternate Procedure Approval
- LPA Agreement to Contribute Funds
- Contractual Agreement for Right of Way Procurement
- Request for Determination of Eligibility
- Utility Consultant Contract Approval
- Prepare Utility Agreement Assembly
- Perform Utility Adjustment
- Determination of Upper Limit
- Utility Payment Process.
Identify roles and responsibilities for utilities, TxDOT District Planning, Design, ROW, Construction, and TxDOT Division personnel for each activity in “The Process” and “Subprocess.” Descriptions of the various participants identified for each activity may be found in the TxDOT Glossary.