Profile Sheet Requirements

A Profile Sheet shall accurately depict the following items:
  • View direction (facing)
  • The entire dimension of the Pole or Service Structure (new/proposed/existing)
  • Existing structure view, if the proposed Broadband Installation will replace or be attached to an existing structure
  • Proposed structure view, or two different adjoining views (e.g., north and west) if it is a new structure
  • All attached Network Node equipment (e.g., antenna, Network Node, ancillary equipment)
  • Node Transport Facility location and depth (if part of the application)
  • Foundation view or reference to Typical sheet for proposed foundations
  • Buried pole depth for new or replaced Pole or Service Structure without foundation
  • Proposed hand boxes, vaults, and hand holes
  • Proposed underground conduits (within 10' of the network support structure)
  • Grounding detail or reference to Typical page
  • Proposed ground-based enclosure
  • Node Position Key to Department Right-of-Way and road alignment for each Profile View (see Figure B-5). This detail does not have to be to scale but must show alignment on a quadrant and reference the street and the ROW perspectives.
  • Roadway features, including driveways, ramps, and sidewalks, to verify Pole location will not interfere with proposed Improvements
  • Minimum depth of cover for proposed power and communications conduit
  • Offset from Department Right-of-Way line to power
All the following items shall be dimensioned:
  • Antenna height above Pole or Service Structure
  • Pole or Service Structure dimension at the base
  • Distance from Department Right-of-Way line
  • Antenna and cabinet offset from Pole or Service Structure
  • Overall height of the Pole or Service Structure above grade
  • The vertical clearance of any adjacent overhanging roadway
  • Ground-based enclosures and height above grade
  • Pole-mounted or Service Structure-mounted enclosures and height above grade
Node Position Key (click in image to see full-size image)
Figure B-5. Node Position Key