General Requirements
Before a LPA can acquire right of way for a project on the state highway system (on-system), the following requirements must be met:
- Texas Transportation Commission (Commission) approves the project.
- The project receives environmental clearance.
- TxDOT approves a right of way map, property descriptions and parcel plats (See theROW Preliminary Procedures for the Authority to Proceed Manual, ).
- Federal and/or state funding for right of way acquisition has been approved.
Once all prerequisites have been met, TxDOT's LPA Coordinator will advise the LPA when it may begin acquisition activities.