Section 2: Project Closeout

Preparation for Closing Right of Way Projects

In order to close out a right of way project, the following must have occurred:
  • all required right of way is acquired;
  • all condemnation cases are closed by a final judgment (including on appeal);
  • all utility adjustments are completed;
  • all relocation assistance is completed;
  • all charges owed by the state are paid;
  • the LPA has requested reimbursement on all eligible expenses; and
  • all LPA records have been reviewed by TxDOT for compliance with the Uniform Act.
Submit the request for final closing of the project to TxDOT along with a certification that the LPA has complied with the applicable laws, regulations and policies. See the ROW Real Estate Acquisition Guide for Local Public Agencies, for an example of the certification.