Timing
The excess aggregate should not be broomed off the roadway
as soon as the rolling is finished. The asphalt is still too soft
and must be allowed to stiffen or cure before brooming. Otherwise,
the broom will strip the aggregate away from the binder. If necessary,
light
brooming
may be performed before opening to traffic to remove excess aggregate
that is not embedded in the asphalt. Final
brooming
should be done as soon as the binder is fully cured: on the same
day or the following morning. Best results are obtained by waiting
until the following morning (as early as possible). Temperatures
are lower during the early hours and the aggregate will be held
more firmly in place with only the excess aggregate removed.